November 20, 2013 BS
14SNOS ll
Cheryl L. Taylor
Bermuda Magisterial District
Off the eastern terminus of Pine Forest Drive
REQUEST: Conditional use approval to permit a communications tower in an Agricultural
(A) District.
PROPOSED LAND USE:
A 199 foot communications tower and associated improvements are planned.
PLANNING COMMISSION RECOMMENDATION
RECOMMEND APPROVAL SUBJECT TO THE CONDITIONS ON PAGE 2.
STAFF RECOMMENDATION
Recommend approval for the following reasons:
A. The proposal conforms to the Comprehensive Plan which supports the location of
telecommunications towers in areas designated for industrial uses, provided the
visual impact of the base of the tower is minimized.
B. The proposal conforms to the Tower Siting Policy which suggests that towers
should be located in areas designated by the Comprehensive Plan for industrial
use, designed for shared use and located away from areas of existing or planned
residential development; and that views of the tower from existing or planned
areas of development should be mininzed.
(NOTES: A. CONDITIONS MAY BE IMPOSED OR THE PROPERTY OWNER
MAY PROFFER CONDITIONS. CONDITIONS NOTED "STAFF/CPC"
WERE AGREED UPON BY BOTH STAFF AND THE COMMISSION.
Pro~Tiding a FIRST CHOICE community through excellence in public ser~Tice
B. UNDER THE FEDERAL TELECOMM[_JNICATIONS ACT,
LOCALITIES CANNOT REGULATE CELL TOWERS ON THE BASIS
OF POSSIBLE HEALTH OR ENVIRONMENTAL EFFECTS OF
RADIO FREQUENCY EMISSIONS.)
CONDITIONS
(STAFF/CPC) 1. The base of the tower shall be enclosed by a minimum six (6) foot
high fence designed to preclude trespassing. The fence shall be
placed so as to provide sufficient room between the fence and the
property line to accommodate evergreen plantings having an initial
height and spacing to provide screening of the base of the tower
and accessory ground-mounted equipment or strictures from
adjacent properties. A detailed plan depicting this requirement
shall be submitted to the Planning Department for approval in
conjunction with final site plan review. (P)
(STAFF/CPC) 2. The color and treatment of the tower shall be as follows:
a. The tower shall be gray or another neutral color, acceptable
to the Planning Department.
b. The tower shall not be lighted unless lighting is required by
the FAA. If lighted, lighting during daylight hours shall be
limited to medium intensity strobe lights with upward
reflection and lighting during night-time hours shall be
limited to soft blinking lights with upward reflection.
c. The tower shall be a monopole stricture. (P)
(STAFF/CPC) 3. Any building or mechanical equipment shall comply with Section
19-570 (b) and (c) and 19-595 of the Zoning Ordinance relative to
architectural treatment of building exteriors and screening of
mechanical equipment. (P)
(NOTE: Section 19-570 (b) and (c) would require the screening of
mechanical equipment located on the building or ground from
adjacent properties and public rights-of--way. Screening would not
be required for the tower or tower-mounted equipment.)
(STAFF/CPC) 4. At such time that the tower ceases to be used for communications
purposes for a period exceeding twelve (12) consecutive months,
the owner/developer shall dismantle and remove the tower and all
associated equipment from the property. (P)
2 14SN0~11-2013N0~'20-BOS-RPT
(STAFF/CPC) 5. With approval of this request, prior to issuance of a final certificate
of occupancy for the proposed tower, the existing tower located on
Tax ID 803-631-Part of 2296, south of this site, shall be removed.
gyp)
GENERAL INFORMATION
T ncati nn
The request property is located off the eastern terminus of Pine Forest Drive, east of
Jefferson Davis Highway. Tax ID 803-631-Part of 2296.
Existing Zonin
A
Size:
1.1 acres
Existing Land Use:
Industrial or vacant
Adj acent Zoning and Land Use:
North, South and East - A; Government (VDOT office and equipment facility)
West - A and I-1; Government (VDOT office and equipment facility) or vacant
UTILITIES; PUBLIC FACILITIES AND COUNTY TRANSPORTATION
This request will have no impact on these facilities.
ENVIRONMENTAL
The precise limits of the Resource Protection Area (RPA) must be established on the property
through a process managed by the Water Quality Section of the Environmental Engineering
Department prior to the submission of a site plan. The site plan must show that the proposed
constriction activities will not encroach into the RPA.
COUNTY COMM[_]NICATIONS
The Zoning Ordinance requires that any stricture over eighty (80) feet in height be reviewed by
the County's Public Safety Review Team for potential detrimental impacts the stricture could
have on the County's Radio Communications System microwave paths. This determination must
be made prior to constriction of the communications tower.
3 14SN0~11-2013N0~'20-BOS-RPT
COUNTY AIIZPORT
A preliminary review of this proposal indicates that, given the approximate location and
elevation of the proposed installation, there will be no adverse affect on the County Airport.
LAND USE
Comprehensive Plan:
The Comprehensive Plan suggests the property is appropriate for Industrial use.
The Public Facilities Plan, an element of the Comprehensive Plan, suggests that
communications tower locations should generally be located to nunimize the impact on
existing or future areas of development. Alsq in areas designated for industrial uses, the
visual impact of the base of the tower should be minimized.
The Tower Siting Policy suggests that towers should be located in areas designated by the
Comprehensive Plan for industrial use. It should be noted that the Commission is
currently evaluating the Tower Siting Policy. They have set a public meeting for October
15, 2013 to discuss the revised policy. As conditioned, this request complies with the
draft policy.
Area Development Trends:
With the exception of Millside Subdivision to the south, the area is characterized by
industrial development and vacant property north, east and west of the request site. It is
anticipated industrial development will continue in this area, as suggested by the Plan.
Zoni ng History:
The property is owned by the Virginia Department of Transportation (VDOT). A
communication tower has been located on the property for many years. When originally
erected the tower was considered an accessory to a permitted use, as it was for use by
VDOT only. Over the years cellular carriers were allowed to co-locate on the tower
stnict~ire and such carriers did not obtain the requisite zoning. A carrier wishes to upgrade
equipment on the tower, and it's been determined the current tower is not stnicturally sound
enough to accommodate the equipment modifications. Therefore, a new tower is proposed
as a replacement for the existing tower.
With the approval of this request, there is the potential for two (2) telecommunications
towers to be located on the property within close proxinuty of each other. While the plan is
to relocate telecommunications equipment from the existing tower onto the new tower and
remove the existing tower, leaving only one (1) tower on the property, Condition 5 is
intended to provide assurance that the existing tower gets removed.
4 14SN0~11-2013N0~'20-BOS-RPT
Development Standards:
The tower site is within the Virginia Department of Transportation (VDOT) office and
equipment complex, behind and adjacent to one of the strictures located on the property.
Driveway access is to be provided out to Pine Forest Drive. The proposed tower is
intended to replace an existing tower currently located near the front of the property.
The request property lies within an Emerging Growth Area. The purpose of the Emerging
Growth District standards is to promote high quality, well-designed projects. However,
because the request property is zoned Agricultural (A), development is not required to
meet the development standards for Emerging Growth Areas. Staff recommends the
imposition of Condition 3, requiring compliance with Emerging Growth Area
requirements relative to the architectural treatment of the proposed equipment building
and screening of mechanical equipment.
Condition 2 requires the proposed communications tower to be a monopole, intended to
minimize its appearance (Attachment). The base of the tower should be secured with a
fence to discourage trespassing and screened to minimize the view from adjacent
properties. (Condition 1)
To ensure that the tower does not become a maintenance problem or an eyesore, the
tower and associated equipment should be removed at such time that it ceases to be used
for communications purposes. (Condition 4)
CONCLUSION
The proposal conforms to the Comprehensive Plan which supports the location of
telecommunications towers in areas designated for industrial uses, provided the visual impact of
the base of the tower is nnimized. In addition, the proposal conforms to the existing Tower
Siting Policy which suggests that towers should be located in areas designated by the
Comprehensive Plan for industrial use; be designed for shared use; be located away from areas
of existing or planned residential development; and that views of the tower from existing or
planned areas of development should be minimized.
Given these considerations, approval is recommended.
CASE HISTORY
Planning Commission Meeting (10/15/13):
The applicant accepted the recommendation. There was no opposition present.
On motion of Mr. Patton, seconded by Mr. Gulley, the Commission recommended
approval subject to the conditions on page 2.
14SN0~11-2013N0~'20-BOS-RPT
AYES: Messrs. Brown, Wallin, Gulley, Patton and Waller.
The Board of Supervisors, on Wednesday, November 20, 2013 beginning at 6:30 p.m., will take
under consideration this request.
14SN0 ~ 11-2013N0~'20-B ( )S-RPT
Q
~_
N
aWc
G
w
N
4
PROP06ED GSM AND
ANtDrNAS
ANTENNA NOTE:
LTE ANTENNA HEIGHT NOT
TO EXCEED EXISTING UMTS
ANTENNA HEIGHTS.
A SfRUCTURAI ANALYSIS OF THIS
TOWER WAS NOT PERFORMED BY
VELOpiEL, N~lC. COPfiRIVCTOR SHALL
REFER TO STRUCTl1RAL ANALYSIS
(IF APPUC/IBLE) AND COORDINATE LTE
ANTENNA AND ASSOCIATED EQUIPMENT
MOUNTN~IG WRH THE SRE CONSTRUCTION
MANAGER AND THE TOWER OWNER.
PROPOSED 18'x2
AT~T EQUIPMENT
SHELTER
LTE ANTENNA
PROP06ED COMPOUND
FENCED
PROPOSED TOWER ELEVATION
NOT TO SCALE
$_
N 1
z ~
v
U
e
14SN0511-1