15SN0660
CASE NUMBER: 15SN0660
APPLICANT: East West Hallsley, LLC
CHESTERFIELD COUNTY, VIRGINIA
Magisterial District: MIDLOTHIAN
ADDENDUM
1115 Mt. Hermon Road
Board of Supervisors (BOS)
Public Hearing Date:
AUGUST 26, 2015
BOS Time Remaining:
365 DAYS
Applicant’s Agent:
Andrew Scherzer
(804-794-0571)
Applicant’s Contact:
JASON FENCHUK
(804-523-4147)
Planning Department Case Manager:
Darla Orr (804-717-6533)
APPLICANT’S REQUEST
Rezoning from Agricultural (A) to Residential (R-15)
A single-family residential subdivision with a maximum of sixty-five (65) lots is planned, yielding a
density of approximately 1.2 dwellings per acre. (Proffered Condition 1)
Notes:
A.The only condition that may be imposed is a buffer condition for the rezoning request. The property
owner may proffer conditions.
B.A revised proffered condition is located in Attachment 1.
ADDENDUM
The purpose of this Addendum is to provide the Applicant’s revised proffered condition and
resulting modified comments from staff. It is important to note that this revision was
submitted after public advertisement of this case. The Board of Supervisors must unanimously
agree to suspend their procedures in order to consider this revised proffered condition.
On August 19, 2015, the applicant submitted a revision to Proffered Condition 5 that revises the
cash proffer allocation to capital facilities. The applicant has proffered to increase the allocation
of the cash proffer payment for the Schools capital facilities to be the full calculated impact. To
facilitate this increase, the applicant would pro-rate a corresponding reduction in the remaining
capital facilities categories. An update to “Financial Impacts on Capital Facilities” and each of the
“Public Facilities” sections is included with this Addendum.
Staff continues to recommend approval of this request, as outlined on the following page.
Providing a FIRST CHOICE community through excellence in public service
RECOMMENDATION
RECOMMEND APPROVAL*
Complies with Comprehensive Plan
Addresses development impacts
STAFF
*Acceptance of the Proffered Conditions 1 – 4 and 6 – 10 in the “Staff
Analysis” and Proffered Condition 5, shown as “MODIFIED” in
Attachment 1 of this Addendum, would be appropriate.
215SN0660-2015JUL21-CPC-RPT
FINANCIAL IMPACT ON CAPITAL FACILITIES
Budget and Management
Staff Contact: Natalie Spillman (717-8767) spillmann@chesterfield.gov
The need for schools, parks, libraries, fire stations and transportation facilities in this area is
identified in the County’s adopted Public Facilities Plan, Thoroughfare Plan and Adopted Capital
Improvement Program and further detailed by specific departments in the applicable sections
of this request analysis.
This proposed development will have an impact on capital facilities. Staff has calculated the
fiscal impact of every new dwelling unit on schools, roads, parks, libraries and fire stations at
$23,418 per unit.
The applicant has requested a rezoning from Agricultural (A) to Residential (R-15) with a
maximum density of 65 dwelling units (Proffered Condition 1). To address the impact of this
development on capital facilities, the applicant has proffered $18,966 per dwelling unit which is
the maximum cash proffer in place. If accepted, the cash proffer would remain at $18,966 for a
period of four years after which it would be escalated by the cumulative change in the Marshall
and Swift Building Cost Index.
In this case, the applicant has proffered the full calculated amount of $9,648 for schools (in lieu
of $7,814), while allocating the remaining balance of the $18,966 pro-rated among the other
facility costs as follows: $911 for parks, $215 for libraries, $583 for fire stations and $7,609 for
roads. While this deviates from the Board’s pro-rated category allocations, staff is supportive of
this proffer as a means to better address the impact of this proposal on school capital facilities.
Note that circumstances relevant to this case, as presented by the applicant, have been
reviewed, and it has been determined that it is appropriate to accept the maximum cash
proffer of $18,966 for each dwelling unit.
Per Dwelling Unit Impact on
65*
Capital Facilities
Potential Units
FacilityApplicant's Proposal
FY15 Calculated Impact
Categories (Current BOS Maximum)
Total $23,418 $18,966
Overall Impact on Capital Facilities
Schools $627,120 $627,120
Parks $87,555 $59,215
Libraries $20,670 $13,975
Fire Stations $55,965 $37,895
Roads $730,860 $494,585
Total $1,522,170 $1,232,790
*Based on proffered density. The actual number of lots and corresponding impact may vary.
315SN0660-2015JUL21-CPC-RPT
PUBLIC FACILITIES
FIRE SERVICE
Staff Contact: Greg Smith (804-706-2012) smithgd@chesterfield.gov
The mission of Fire and Emergency Medical Services (EMS) is to protect life, property and the
environment through a comprehensive fire and life safety program that ensures an adequate
and timely response to emergencies. The Public FacilitiesPlan, as part of the Comprehensive
Plan, indicates:
County-wide Fire & EMS Service Information & Needs
New 5
Recommendations for Fire Stations
by 2022
Replacement/Revitalization 4
Fire 24%
1
2011 Incidents as a percent of total
EMS (Emergency Medical Services) 76%
Fire/EMS Increases in Call Volume
44%
from 2001 and 2011
County Population Increase from
17%
2001 to 2011
1
With the aging of population, medical emergency incidents are expected to increase faster than the rate of
population growth over time.
Fire Service - Project Impacts
Estimated Number of Calls for
1
Service Annually
Reference “Financial Impact on Capital Facilities”
Applicant’s Proposal to Address
discussion on Page 3
1
Impacts
Proffered Condition 5
1
The financial impact of residential development on fire facilities is addressed in the “Financial Impact on Capital
Facilities” section of the report.
Additional Information:
When the property is developed, the number of hydrants, quantity of water needed for fire
protection, and access requirements will be evaluated during the plans review process.
Information relative to nearby fire and emergency service facilities can be found in Attachment
2.
415SN0660-2015JUL21-CPC-RPT
PARKS AND RECREATION
Staff Contact: Brian Geouge (318-8720) geougeb@chesterfield.gov
The County supports a high-quality park system to provide residents and visitors with equitable
access to active and passive recreation opportunities. The Public Facilities Plan, as part of the
Comprehensive Plan, indicates:
County-wide Parks and Recreation Needs
Park TypeNumber of New Parks Aggregate Acreage
Regional 3600
Community10 790
Neighborhood 9180
Special Purpose 3 1 -
Urban 2 - -
Linear 3 - -
1
The Public Facilities Plan notes facility recommendations for water-based parks. All other facilities are acquired
and developed on a site-by-site basis.
2
Facilities are recommended in urban areas where there is limited acreage available for park development.
3
Facility needs are assessed on a site-by-site basis as recommended in the Public Facilities Plan.
Parks and Recreation – Project Impacts
5.9 Acres of Regional, Community and/or Neighborhood
2012 County Level of Service
parkland per 1,000 persons
9 Acres of Regional, Community and/or Neighborhood
Target Level of Service
parkland per 1,000 persons
Reference “Financial Impact On Capital Facilities”
discussion on Page 3
Applicant’s Proposal to Address
1
Impacts
Proffered Condition 5
1
The financial impact of residential development on parks facilities is addressed in the “Financial Impact on Capital
Facilities” section of the report.
Additional Information:
Information relative to nearby parks and recreation facilities can be found in Attachment 2.
515SN0660-2015JUL21-CPC-RPT
LIBRARIES
Staff Contact: Debra Winecoff (751-4475)winecoffd@chesterfield.gov
The public library system’s role in the county has expanded beyond its traditional function as a
resource for information and materials, and now serves as a community gathering place for
educational, cultural and informational services; community support during emergencies;
economic development; and revitalization activities.The Public Facilities Plan, as part of the
Comprehensive Plan,indicates:
County-wide Library Needs
Facility ActionCounty-wide Facility Needs
Expand or Replace 5 Libraries
Construction of New 5 Libraries
Facilities
1 Community Arts Center
Libraries -Project Impacts
Applicant’s Proposal to Reference “Financial Impact On Capital Facilities” discussion
1
Address Impacts on Page 3
Proffered Condition 5
1
The financial impact of residential development on library facilities is addressed in the “Financial Impact on
Capital Facilities” section of the report.
Additional Library Information:
Information relative to nearby library facilities can be found in Attachment 2
615SN0660-2015JUL21-CPC-RPT
SCHOOLS
Staff Contact: Atonja Allen (804-318-8740) atonja_allen@ccpsnet.net
High performing, high quality public schools contribute to the quality of life and economic
vitality of the County. The Comprehensive Plan suggests a greater focus should be placed on
linking schools with communities by providing greater access, flexible designs and locations that
better meet the needs of the communities in which they are located. The Public Facilities Plan,
as part of the Comprehensive Plan, indicates:
County-wide School Needs
School Types Facilities to Revitalize/Replace New Facilities
Elementary 16 3
Middle 62
High 23
Technical - 1
Schools -Project Impacts
Elementary 14
Middle 7
Average Student Yield
High 10
Total 31
Applicant’s Proposal to Reference “Financial Impact On Capital Facilities” discussion on
1
Address Impacts Page 3
Proffered Condition 5
1
The financial impact of residential development on school facilities is addressed in the “Financial Impact on
Capital Facilities” section of the report.
Additional Information:
After review of this request, based on current school assignments and student enrollment the
proposed rezoning case will have an impact on schools. It is possible that over time this case,
combined with other tentative residential developments and other zoning cases in the area will
continue to push these schools to their capacity and therefore impact the capacity of facilities
division-wide.
Information relative to schools currently serving area can be found in Attachment 2.
715SN0660-2015JUL21-CPC-RPT
COUNTY DEPARTMENT OF TRANSPORTATION
Staff Contact: Jim Banks (804) 748-1037 banksj@chesterfield.gov
The Comprehensive Plan, which includes the Thoroughfare Plan, identifies county-wide
transportation needs that are expected to mitigate traffic impacts of future growth. The
anticipated traffic impact of the proposal has been evaluated and recommendations are
detailed in the chart below:
Recommendation Applicant’s Proposal
Offered as Recommended
Right of Way Dedication
90 foot widefor Baybon Road through the property.
Proffered Condition 6
Offered as Recommended.
Vehicular Access Control
Approval of an access plan for Baybon Road.
Proffered Condition 7
Road Improvements Offered as Recommended
Construction of 2 lanes for Baybon Road from Bright
Walton Road to the western property line.
Left and right turn lanes along Bright Walton Road at
Baybon Road intersection and along Baybon Road at
each site access.
Proffered Condition 8
Cash ProfferReference “Financial Impact On
Capital Facilities” discussion on
Page 3
Proffered Condition 5
815SN0660-2015JUL21-CPC-RPT
ATTACHMENT 1
PROFFERED CONDITION 5
Notes:
A.“CPC” – Original Proffered Condition 5 –As recommendedby the Planning Commission
B.“MODIFIED” –Revised Proffered Condition 5 – Submitted by Applicant on August 19, 2015
“CPC”5. Cash Proffer. For each dwelling unit, the applicant, sub-divider, or assignee(s)
shall pay the following to the County of Chesterfield, prior to the issuance of a
building permit for infrastructure improvements within the cash proffer service
district for the property, unless state law prevents enforcement of that timing:
A.$18,966.00 per dwelling unit for the period beginning the July 1
preceding the Board of Supervisors’ approval of the case through July 1
four years later, at which point the amount will be adjusted for the
cumulate change in the Marshall and Swift Building Cost Index during
that time period.
B.Thereafter, the per dwelling unit cash proffer amount shall be
automatically adjusted, annually, by the annual change in the Marshall
and Swift Building Cost Index on July 1 of each year.
C.Cash proffer payments shall be spent for the purposes proffered or as
otherwise permitted by law.
D.Should Chesterfield County impose impact fees at any time during the life
of the development that are applicable to the Property, the amount paid
in cash proffers shall be in lieu of or credited toward, but not be in
addition to, any impact fees in a manner determined by the County. (B)
5.Cash Proffer. For each dwelling unit, the applicant, sub-divider, or assignee(s)
“MODIFIED”
shall pay the following to the County of Chesterfield, prior to the issuance of a
building permit for infrastructure improvements within the cash proffer service
district for the property, unless state law prevents enforcement of that timing:
A.$18,966.00 per dwelling unit for the period beginning the July 1
preceding the Board of Supervisors’ approval of the case through July 1
four years later, at which point the amount will be adjusted for the
cumulative change in the Marshall and Swift Building Cost Index during
that time period. The $18,966 will be allocated pro-rata among the
facility costs as follows: $9,648.00 for schools, $911.00 for parks and
recreation, $215.00 for library facilities, $7,609.00 for roads, and $583.00
for fire stations.
B.Thereafter, the per dwelling unit cash proffer amount shall be
automatically adjusted, annually, by the annual change in the Marshall
and Swift Building Cost Index on July 1 of each year.
915SN0660-2015JUL21-CPC-RPT
C.Cash proffer payments shall be spent for the purposes proffered or as
otherwise permitted by law.
D.Should Chesterfield County impose impact fees at any time during the life
of the development that are applicable to the Property, the amount paid
in cash proffers shall be in lieu of or credited toward, but not be in
addition to, any impact fees in a manner determined by the County.
1015SN0660-2015JUL21-CPC-RPT
ATTACHMENT 2
SUPPLEMENTAL PUBLIC FACILITIES STATISTICS
Schools Currently Serving Area
Watkins
Midlothian Midlothian
Elementary
Middle School High School
School
Capacity
Functional Functional Functional
rship
MembershipMembership
% Capacity% Capacity% Capacity
Current
CapacityCapacity
Capacity
Categories
and
Membe
Projected
2
Figures
2014 1011 8181241225 1506 81 14721569 94
2015 1033 -1261206 - 80 1548- 99
2016 1051 -1281213 - 81 1591- 101
2021 1072 -1311211 - 80 1689- 108
Trailers Number of
3 - 0
1
Trailers
1
Trailers are not identified in the staff report for schools under 90% capacity.
2
Disclaimer: Please note that Projected Membership AND Functional Capacity are updated on an ANNUAL BASIS.
They are based on the September 30 membership and Space Utilization Study Report for a given year. School
boundary adjustments may be made to address over capacity levels.
1115SN0660-2015JUL21-CPC-RPT
CASE NUMBER: 15SN0660
APPLICANT: East West Hallsley, LLC
CHESTERFIELD COUNTY, VIRGINIA
Magisterial District: MIDLOTHIAN
STAFF’S ANALYSIS
1115 MT. HERMON ROAD
AND
RECOMMENDATION
Board of Supervisors (BOS)
Public Hearing Date:
AUGUST 26, 2015
BOS Time Remaining:
365 DAYS
Applicant’s Agent:
Andrew Scherzer
(804-794-0571)
Applicant’s Contact:
JASON FENCHUK
(804-523-4147)
Planning Department Case Manager:
Darla Orr (804-717-6533)
APPLICANT’S REQUEST
Rezoning from Agricultural (A) to Residential (R-15)
A single-family residential subdivision with a maximum of sixty-five (65) lots is planned, yielding a
density of approximately 1.2 dwellings per acre. (Proffered Condition 1)
Notes:
A. The only condition that may be imposed is a buffer condition. The owner(s) may proffer other
conditions.
B.Proffered conditions are located in Attachment 1
RECOMMENDATION
RECOMMEND APPROVAL
Complies with Comprehensive Plan
STAFF
Addresses development impacts
Providing a FIRST CHOICE community through excellence in public service
SUMMARY OF IDENTIFIED ISSUES
Department Issue
PLANNING -
BUDGET AND
-
MANAGEMENT
FIRE -
PARKS AND
-
RECREATION
LIBRARIES -
SCHOOLS -
CDOT -
VDOT -
UTILITIES -
ENVIRONMENTAL
-
ENGINEERING
215SN0660-2015JUL21-CPC-RPT
315SN0660-2015JUL21-CPC-RPT
Map 2: Comprehensive Plan
Classification: SUBURBAN RESIDENTIAL I
The designation suggests the property is appropriate for residential use of 2.0 dwelling units per
acre or less.
Map 3: Surrounding Land Uses & Development
Single family
Hull Street Rd
residential – Hallsley
Single family
residential on large
acreage parcels or
Brightwalton Rd
vacant
415SN0660-2015JUL21-CPC-RPT
PLANNING
Staff Contact: Darla Orr (804-717-6533) orrd@chesterfield.gov
PROPOSAL
A single-family residential subdivisionto be developed in conjunction with the Hallsley subdivision
is planned. The following provides an overview of the development’s design standards:
GeneralOverview
Requirements Details
Maximum of 65 dwelling units, yielding approximately 1.2
Density
dwelling unitsper acre
Proffered Condition 1
Within recorded open space
Buffers
Proffered Condition 4
Yard trees, foundation planting and sodded yards
Landscaping
Proffered Condition 3.B
Minimum of 2,000 gross square feet
House Size
Proffered Condition 2
Compatible with styles within Hallsley with varied styles
Architectural Treatment along streets
Proffered Condition 3.C.1 and 2
Permitted materials established for roofs, facades and
Building Materialsporches; vinyl only permitted in soffits and eaves
Proffered Conditions 3.C.3 and 4, 3.D, 3.E and 3.F
Hardscaped
Driveways
Proffered Condition 3.A
Limited hours; builders and citizens notified
Construction Hours
Proffered Condition 9
Clarifies timing for approval of individual building and lot
Approval Prior to Building Permit
landscaping plans
Issuance
Proffered Condition 3.G
515SN0660-2015JUL21-CPC-RPT
FINANCIAL IMPACT ON CAPITAL FACILITIES
Budget and Management
Staff Contact: Natalie Spillman (717-8767) spillmann@chesterfield.gov
The need for schools, parks, libraries, fire stations and transportation facilities in this area is
identified in the County’s adopted Public Facilities Plan, Thoroughfare Plan and Adopted Capital
Improvement Program and further detailed by specific departments in the applicable sections
of this request analysis.
This proposed development will have an impact on capital facilities. Staff has calculated the
fiscal impact of every new dwelling unit on schools, roads, parks, libraries and fire stations at
$23,418per unit.
The applicant has requested a rezoning from agricultural (A) to Residential (R-15) with a
maximum density of 65 dwelling units (Proffered Condition 1). To address the impact of this
development on capital facilities, the applicant has proffered $18,966 per dwelling unit which is
the maximum cash proffer in place. If accepted, the cash proffer would remain at $18,966 for a
period of four years after which it would be escalated by the cumulative change in the Marshall
and Swift Building Cost Index
Note that circumstances relevant to this case, as presented by the applicant, have been
reviewed, and it has been determined that it is appropriate to accept the maximum cash
proffer of $18,966 for each dwelling unit.
65*
Per Dwelling Unit Impact on Capital Facilities
Potential Units
FacilityApplicant's Proposal (Current BOS
FY16 Calculated Impact
Categories Maximum)
Total $23,414 $18,966
Overall Impact on Capital Facilities
Schools $627,120 $543,660
Parks $87,490 $76,960
Libraries $20,475 $19,695
Fire Stations $55,965 $45,565
Roads $730,860 $546,910
Total $1,521,910 $1,232,790
*Based on proffered density. The actual number of lots and corresponding impact may vary.
615SN0660-2015JUL21-CPC-RPT
PUBLIC FACILITIES
FIRE SERVICE
Staff Contact: Greg Smith (804-706-2012) smithgd@chesterfield.gov
The mission of Fire and Emergency Medical Services (EMS) is to protect life, property and the
environment through a comprehensive fire and life safety program that ensures an adequate
and timely response to emergencies. The Public Facilities Plan, as part of the Comprehensive
Plan, indicates:
County-wide Fire & EMS Service Information & Needs
New 5
Recommendations for Fire Stations
by 2022
Replacement/Revitalization 4
Fire 24%
1
2011 Incidents as a percent of total
EMS (Emergency Medical Services) 76%
Fire/EMS Increases in Call Volume
44%
from 2001 and 2011
County Population Increase from
17%
2001 to 2011
1
With the aging of population, medical emergency incidents are expected to increase faster than the rate of
population growth over time.
Fire Service - Project Impacts
Estimated Number of Calls for
1
Service Annually
Applicant’s Proposal to Address
Offered in Accordance with Policy
1
Impacts
Proffered Condition 5
1
The financial impact of residential development on fire facilities is addressed in the “Financial Impact on Capital
Facilities” section of the report.
Additional Information:
When the property is developed, the number of hydrants, quantity of water needed for fire
protection, and access requirements will be evaluated during the plans review process.
Information relative to nearby fire and emergency service facilities can be found in Attachment
2.
715SN0660-2015JUL21-CPC-RPT
PARKS AND RECREATION
Staff Contact: Brian Geouge (318-8720) geougeb@chesterfield.gov
The County supports a high-quality park system to provide residents and visitors with equitable
access to active and passive recreation opportunities. The Public Facilities Plan, as part of the
Comprehensive Plan, indicates:
County-wide Parks and Recreation Needs
Park TypeNumber of New Parks Aggregate Acreage
Regional 3600
Community10 790
Neighborhood 9180
Special Purpose 3 1 -
Urban 2 - -
Linear 3 - -
1
The Public Facilities Plan notes facility recommendations for water-based parks. All other facilities are acquired
and developed on a site-by-site basis.
2
Facilities are recommended in urban areas where there is limited acreage available for park development.
3
Facility needs are assessed on a site-by-site basis as recommended in the Public Facilities Plan.
Parks and Recreation – Project Impacts
5.9 Acres of Regional, Community and/or Neighborhood
2012 County Level of Service
parkland per 1,000 persons
9 Acres of Regional, Community and/or Neighborhood
Target Level of Service
parkland per 1,000 persons
Applicant’s Proposal to Address
Offered in Accordance with Policy
1
Impacts
Proffered Condition 5
1
The financial impact of residential development on parks facilities is addressed in the “Financial Impact on Capital
Facilities” section of the report.
Additional Information:
Information relative to nearby parks and recreation facilities can be found in Attachment 2.
815SN0660-2015JUL21-CPC-RPT
LIBRARIES
Staff Contact: Debra Winecoff (751-4475)winecoffd@chesterfield.gov
The public library system’s role in the county has expanded beyond its traditional function as a
resource for information and materials, and now serves as a community gathering place for
educational, cultural and informational services; community support during emergencies;
economic development; and revitalization activities. The Public Facilities Plan, as part of the
Comprehensive Plan,indicates:
County-wide Library Needs
Facility ActionCounty-wide Facility Needs
Expand or Replace 5 Libraries
Construction of New 5 Libraries
Facilities
1 Community Arts Center
Libraries -Project Impacts
Applicant’s Proposal to
Offered in Accordance with Policy
1
Address Impacts
Proffered Condition 5
1
The financial impact of residential development on library facilities is addressed in the “Financial Impact on
Capital Facilities” section of the report.
Additional Library Information:
Information relative to nearby library facilities can be found in Attachment 2
915SN0660-2015JUL21-CPC-RPT
SCHOOLS
Staff Contact: Atonja Allen (804-318-8740) atonja_allen@ccpsnet.net
High performing, high quality public schools contribute to the quality of life and economic
vitality of the County. The Comprehensive Plan suggests a greater focus should be placed on
linking schools with communities by providing greater access, flexible designs and locations that
better meet the needs of the communities in which they are located. The Public Facilities Plan,
as part of the Comprehensive Plan, indicates:
County-wide School Needs
School Types Facilities to Revitalize/Replace New Facilities
Elementary 16 3
Middle 62
High 23
Technical - 1
Schools -Project Impacts
Elementary 14
Middle 7
Average Student Yield
High 10
Total 31
Applicant’s Proposal to
Offered in Accordance with Policy
1
Address Impacts
Proffered Condition 5
1
The financial impact of residential development on school facilities is addressed in the “Financial Impact on
Capital Facilities” section of the report.
Additional Information:
After review of this request, based on current school assignments and student enrollment the
proposed rezoning case will have an impact on schools. It is possible that over time this case,
combined with other tentative residential developments and other zoning cases in the area will
continue to push these schools to their capacity and therefore impact the capacity of facilities
division-wide.
Information relative to schools currently serving area can be found in Attachment 2.
1015SN0660-2015JUL21-CPC-RPT
COUNTY DEPARTMENT OF TRANSPORTATION
Staff Contact: Jim Banks (804) 748-1037 banksj@chesterfield.gov
The Comprehensive Plan, which includes the Thoroughfare Plan, identifies county-wide
transportation needs that are expected to mitigate traffic impacts of future growth. The
anticipated traffic impact of the proposal has been evaluated and recommendations are
detailed in the chart below:
RecommendationApplicant’s Proposal
Offered as Recommended
Right of Way Dedication
90 foot widefor Baybon Road through the property.
Proffered Condition 6
Offered as Recommended.
Vehicular Access Control
Approval ofan access plan for Baybon Road.
Proffered Condition 7
Road Improvements Offered as Recommended
Construction of 2 lanes for Baybon Road from Bright
Walton Road to the western property line.
Left and right turn lanes along Bright Walton Road at
Baybon Road intersection and along Baybon Road at
each site access.
Proffered Condition 8
Cash ProfferOffered in Accordance with
Policy
Proffered Condition 5
VIRGINIA DEPARTMENT OF TRANSPORTATION
Staff Contact: Brian Lokker (804-674-2384) brian.lokker@vdot.virginia.gov
To date, no comments have been received.
1115SN0660-2015JUL21-CPC-RPT
WATER AND WASTEWATER SYSTEMS
Staff Contact: Jamie Bland (804-751-4439) blandj@chesterfield.gov
The proposal’s impacts on the County’s utility system are detailed in the chart below:
Water and Wastewater Systems
Currently Size of Existing LineConnection Required by County Code?
Serviced?
Water No 12”Yes
Wastewater No 21” & 30” Yes
Map 5: Existing Water & Wastewater Systems
1215SN0660-2015JUL21-CPC-RPT
ENVIRONMENTAL
Drainage, Erosion and Water Quality
Staff Contact: Doug Pritchard (804-748-1028) pritchardd@chesterfield.gov
The Natural Resource Inventory (NRI) has been approved by the Environmental Engineering
Department.
1315SN0660-2015JUL21-CPC-RPT
CASE HISTORY
Applicant Submittals
5/11/15 Application submitted
Community Meeting
6/4/15 Issues Discussed:
Development part of Hallsely subdivision
Over-crowded schools
Adequate recreational facilities
Planning Commission Meeting
7/21/2015 Applicant Comments:
Applicant would be willing to offer an increase cash proffer amount to
address school impacts which would be closer to the calculated costs
Citizen Comments:
Questioned accuracy of data on development’s projected student yield
Appreciate applicants willingness to offset impact on schools which are
overcrowded
Not against growth and Hallsley is a great neighborhood
Concerned land owners are negatively impacted because of schools lack
of school planning
Commission Discussion:
In response to questions from the Commission, Budget advised the
calculated impact for schools is $9,648; therefore, cash proffer greater
than the cost would not be acceptable
Mr. Waller recognized that the focus is on over-crowding at Watkins
Elementary School and noted he has received many questions about
timing of the replacement school for Watkins Elementary
Proposal is offering cash proffer in accordance with Cash Proffer Policy
Recommendation – APPROVAL AND ACCEPTANCE OF THE PROFFERED
CONDITIONS IN ATTACHMENT 1
Motion: Waller Seconded: Wallin
AYES: Gulley, Waller, Brown and Wallin
ABSENT: Patton
The Board of Supervisors on Wednesday, August 26, 2015, beginning at 6:30 p.m., will
consider this request.
1415SN0660-2015JUL21-CPC-RPT
ATTACHMENT 1
PROFFERED CONDITIONS
1.A maximum of sixty-five (65) lots shall be permitted. (P)
2.All dwellings shall have a minimum gross floor area of 2,000 square feet. (P)
3.Architectural/Design Elements.
A.Driveways
1.Driveways: All private driveways serving residential uses shall be hardscape with
stained brushed concrete, aggregate, stamped concrete or pavers.
B.Landscaping and Yards
1.Supplemental Trees: Three (3) yard trees shall be planted or retained in the front
yard of each dwelling with a minimum diameter of 2.5 inches measured at breast
height (4’10” above the ground).
2.Front Yards & Side Yards: Except for the foundation planting bed, all front and side
yards shall be sodded and irrigated.
3.Front Foundation Planting Beds: Foundation planting is required along the entire
front façade of all dwelling units, and shall extend along all sides facing a street.
Foundation planting beds shall be a minimum of 4’ wide from the unit foundation.
Planting beds shall include medium shrubs spaced a maximum of four (4) feet apart.
Unit corners shall be visually softened with vertical accent shrubs (4’-5’) or small
evergreen trees (6’-8’) at the time of planting.
C. Architecture and Materials
1.Style and Form: The architectural styles shall be interpretations of traditional
Richmond architecture, using forms and elements compatible with those in Hallsley
such as Georgian, Classical Revival Colonial, Greek Revival, Queen Anne, Tudor, and
Craftsman Styles.
2.Repetition: Dwellings with the same elevations may not be located adjacent to,
directly across from, or diagonally across from each other on the same street. This
requirement does not apply to units on different streets backing up to each other.
3.Foundations: The exposed portion of any foundation shall be brick, stone or stucco.
Step down siding will not be permitted.
4.Exterior Façades: Acceptable siding materials include brick, stone, masonry, stucco
synthetic stucco (E.I.F.S), and approved horizontal lap siding or architectural
shingles. Horizontal lap siding may be manufactured from cement fiber board. Vinyl
1515SN0660-2015JUL21-CPC-RPT
material is not permitted except in soffit and eave locations. Additional siding
requirements:
a.Where a dwelling borders more than one street, all street-facing facades
shall be finished in the same materials.
b.Cementitious is permitted in traditional wide reveal styles only, unless
otherwise approved by the Architectural Board for special design
conditions.
D. Roof Material: Roofing material shall be dimensional architectural shingles or better
with a minimum 30 year warranty.
E. Porches, Stoops and Decks
1.Front Porches: All front entry stoops and front porches shall be constructed with
continuous masonry foundation wall or on 12”x12” masonry piers. Extended
front porches shall be a minimum of six (6)’ deep. Space between piers under
porches shall be enclosed with framed lattice panels. Handrails and railings shall
be finished painted wood or metal railing with vertical pickets or swan balusters.
Pickets shall be supported on top and bottom rails that span between columns.
2.Rear Porches/Screen Porches: All rear porches if screen and/or covered shall be
constructed with masonry piers to match either the foundation or façade
material of the house. Rear porches that are not enclosed must be stained or
painted and can be constructed with typical wood piers.
F. Front Porch Flooring: Porch flooring may be concrete, exposed aggregate concrete, or a
finished paving material such as stone, tile or brick, finished (stained dark) wood, or
properly trimmed composite decking boards. Unfinished treated wood decking is not
acceptable. All front steps shall be masonry or stained/painted wood.
G.Approval Prior to Building Permit Issuance: All items in Proffered Conditions 2 and 3
shall be approved prior to the issuance of a building permit for each permit. (BI and P)
4.All required buffers shall be located within recorded open space. (P)
5.Cash Proffer. For each dwelling unit, the applicant, sub-divider, or assignee(s) shall pay the
following to the County of Chesterfield, prior to the issuance of a building permit for
infrastructure improvements within the cash proffer service district for the property, unless
state law prevents enforcement of that timing:
A.$18,966.00 per dwelling unit for the period beginning the July 1 preceding the Board of
Supervisors’ approval ofthe case through July 1 four years later, at which point the
1615SN0660-2015JUL21-CPC-RPT
amount will be adjusted for the cumulate change in the Marshall and Swift Building Cost
Index during that time period.
B.Thereafter, the per dwelling unit cash proffer amount shall be automatically adjusted,
annually, by the annual change in the Marshall and Swift Building Cost Index on July 1 of
each year.
C.Cash proffer payments shall be spent for the purposes proffered or as otherwise
permitted by law.
D.Should Chesterfield County impose impact fees at any time during the life of the
development that are applicable to the Property, the amount paid in cash proffers shall
be in lieu of or credited toward, but not be in addition to, any impact fees in a manner
determined by the County. (B)
6.In conjunction with recordation of the initial subdivision plat, a ninety (90) foot wide right-
of-way for an east/west major arterial (“Baybon Road”) from the eastern property line to
the western property line shall be dedicated, free and unrestricted, to and for the benefit of
Chesterfield County. The exact location and alignment of this right-of-way shall be
approved by the Transportation Department. (T)
7.Prior to any tentative subdivision approval, an access plan for Baybon Road shall be
submitted to and approved by the Transportation Department. Access for the property
shall conform to the approved access plan.(T)
8.The developer shall be responsible for the following road improvements:
A.Construction of two (2) lanes of Baybon Road to VDOT Urban Minor Arterialstandards
(50 MPH) with modifications approved by the Transportation Department, from Bright
Walton Road to the western property line.
B.Construction of left and right turn lanes along Bright Walton Road at the Baybon Road
intersection, and along Baybon Road at each approved access based on Transportation
Department standards.
C.Dedication to Chesterfield County, free and unrestricted, of any additional right-of-way
(or easements) required for the improvements identified in this Proffered Condition. (T)
9.Limitations on Timing of Construction Activity
A. Permitted Hours For Construction:
1.Construction activity shall be limited to between the hours of 7:00 a.m. and 7:00
p.m. Monday through Friday; 7:00 a.m. to 6:00 p.m. on Saturday; and 8:00 a.m. to
5:00 p.m. on Sunday. For the purpose of this condition, construction activity shall be
considered land clearing; grading; installation of infrastructure (such as roads,
utilities and storm drainage); and construction of a dwelling on a vacant lot.
2.This condition is not intended to restrict the hours of home construction (such as
with additions or alterations) once a dwelling is occupied as a residence.
1715SN0660-2015JUL21-CPC-RPT
3.Prior to commencing initial construction activity, these restrictions shall be posted in
English and Spanish on 2’ X 2’ signs that are clearly legible from the public rights of
way at the entrances into the development. Such signs shall be maintained by the
developer and shall remain until all construction activity is complete.
B. Written Notification Prior To Commencing Construction:
Prior to initial construction activity, the Developer shall notify all adjacent property
owners in writing of the anticipated date construction activity will commence.
C. Evidence of Performance:
Prior to the issuance of a land disturbance permit, the Developer shall provide written
confirmation to the Environmental Engineering Department that the sign postings and
written notifications have occurred as required by this condition. (P & EE)
10.Prior to any subdivision construction plan approval, a phasing plan for the required road
improvements, as identified in Proffered Condition 9, shall be submitted to and approved
by the Transportation Department. (T)
1815SN0660-2015JUL21-CPC-RPT
ATTACHMENT 2
SUPPLEMENTAL PUBLIC FACILITIES STATISTICS
Schools Currently Serving Area
Watkins
Midlothian Midlothian
Elementary
Middle School High School
School
Capacity
Functional Functional Functional
MembershipMembershipMembership
% Capacity% Capacity% Capacity
Current
ty
CapacityCapacity
Categories
Capaci
and
Projected
2
Figures
2014 1011 8181241225 1506 81 14721569 94
2015 1033 -1261206 - 80 1548- 99
2016 1051 -1281213 - 81 1591- 101
2021 1072 -1311211 - 80 1689- 108
Trailers Number of
3 - 0
1
Trailers
1
Trailers are not identified in the staff report for schools under 90% capacity.
2
Disclaimer: Please note that Projected Membership AND Functional Capacity are updated on an ANNUAL BASIS.
They are based on the September 30 membership and Space Utilization Study Report for a given year. School
boundary adjustments may be made to address over capacity levels.
Nearby Public Facilities
Fire Station Swift Creek Fire Station, Company Number 16
EMS Facility Swift Creek Fire Station, Company Number 16
Library Clover Hill and Midlothian Libraries
Parks & Recreation Clover Hill Athletic Complex
1915SN0660-2015JUL21-CPC-RPT