STAFF’S ANALYSIS
1900 Twilight Lane
AND
RECOMMENDATION
Board of Supervisors (BOS)
Public Hearing Date:
OCTOBER 28, 2015
BOS Time Remaining:
365 DAYS
Applicant’s Agent:
ANDREW M. SCHERZER
(804-794-0571)
Applicant’s Contact:
ROBERT W. THOMAS
(804-897-5488)
Planning Department Case Manager:
DARLA ORR (804-717-6533)
APPLICANT’S REQUEST
Amendment of zoning (Case 06SN0141) relative to reduction of cash proffers in a Residential (R-
12) District. Specifically, the applicant requests to amend Proffered Condition 2 of Case
06SN0141 to reduce the cash proffer to the Board’s maximum acceptable cash proffer and to
delay the escalator as outlined in the Cash Proffer Policy.
A single-family residential subdivision with a maximum of 45 dwelling units, yielding 1.67
dwelling units per acre, is planned.
Notes:
A.The only condition that may be imposed is a buffer condition. The property owner may proffer
conditions.
B.Proffered conditions and conditions of Case 06SN0141 are located in Attachments 1 and 2.
RECOMMENDATION
PLANNING RECOMMEND APPROVAL
COMMISSION
9/15/2015
RECOMMEND APPROVAL
STAFF
Addresses development impacts
Providing a FIRST CHOICE community through excellence in public service
SUMMARY OF IDENTIFIED ISSUES
Department Issue
PLANNING
BUDGET AND
MANAGEMENT
FIRE
PARKS AND
RECREATION
LIBRARIES
SCHOOLS
CDOT
VDOT
UTILITIES
ENVIRONMENTAL
ENGINEERING
216SN0517-2015OCT28-BOS-RPT
316SN0517-2015OCT28-BOS-RPT
Map 2: Comprehensive Plan
Classification: SUBURBAN RESIDENTIAL II
The designation suggests the property is appropriate for single family residential use of 2.0 to 4.0 dwellings
per acre.
Map 3: Surrounding Land Uses & Development
Twilight Lane
Single family residential use
–Surreywood and Stonemill
Single family residential
use –Three Pines &
Providence Pines
S Twilight Lane
Oxer Road
Single family
residential use –
Foxberry
416SN0517-2015OCT28-BOS-RPT
PLANNING
Staff Contact: Darla Orr (804-717-6533) orrd@chesterfield.gov
ZONING HISTORY
Case Number BOS Action Request
Rezone A to R-12; Single family development with
maximum of 45 lots (1.67 units per acre)
Waiver to street connectivity to Twilight Lane
(north of request property); approved to avoid cut-
through
APPROVED
Approved conditions:
06SN0141
4/26/2006
- Minimum foundation and front porch treatment
- Minimum house size (gross floor area) - 1,800
square feet
-Limit on hours for construction activity
- Cash proffer of $15,600 per dwelling unit
Attachment 2
516SN0517-2015OCT28-BOS-RPT
FINANCIAL IMPACT ON CAPITAL FACILITIES
Budget and Management
Staff Contact: Natalie Spillman (717-8767) spillmann@chesterfield.gov
The need for schools, parks, libraries, fire stations and transportation facilities in this area is
identified in the County’s adopted Public Facilities Plan, Thoroughfare Plan and Adopted Capital
Improvement Program and further detailed by specific departments in the applicable sections
of this request analysis.
This proposed development will have an impact on capital facilities. Staff has calculated the
fiscal impact of every new dwelling unit on schools, roads, parks,libraries and fire stations at
$23,418 per unit.
The original zoning case (06SN0141) was approved in April 2006 with a density of 45 units and
with the maximum cash proffer at the time of $15,600 per dwelling unit (currently escalated by
the Marshall and Swift Building Cost Index to $22,734). The applicant has requested amend the
previously approved case relative to the current maximum of $18,966 per dwelling unit.
While appropriate to maintain the cash proffer approved with case 06SN0141, the Board of
Supervisors has set the current cash proffer at $18,966, an amount lower than what was
approved with the original case. Staff supports the request to reduce the cash proffer to
$18,966 per dwelling unit. If accepted, the amended cash proffer would remain fixed for a
period of four years after which it would be escalated by the cumulative change in the Marshall
and Swift Building Cost Index.
Note that circumstances relevant to this case, as presented by the applicant, have been
reviewed, and it has been determined that it is appropriate to accept the maximum cash
proffer of $18,966 for each dwelling unit.
Per Dwelling Unit Impact on Capital
45
Facilities
Potential Units
Facility Cash Proffer on Existing Applicant's Proposal
FY16 Calculated Impact
Categories Zoning (Current BOS Maximum)
Schools $9,648 $7,771 $7,814
Parks $1,347 $877 $1,091
Libraries $318 $507 $258
Fire
$861 $589 $697
Stations
Roads $11,244 $12,990 $9,106
Total $23,418 $22,734 $18,966
616SN0517-2015OCT28-BOS-RPT
Overall Impact on Capital Facilities
Schools $434,160 $349,695 $351,630
Parks $60,615 $39,465 $49,095
Libraries $14,310 $22,815 $11,610
Fire Stations $38,745 $26,505 $31,365
Roads $505,980 $584,550 $409,770
Total $1,053,810 $1,023,030 $853,470
*Based on a proffered maximum of 45 units per zoning case 06SN0141. Actual number of units
and corresponding impact may vary.
716SN0517-2015OCT28-BOS-RPT
PUBLIC FACILITIES
FIRE SERVICE
Staff Contact: Anthony Batten (717-6167)battena@chesterfield.gov
The mission of Fire and Emergency Medical Services (EMS) is to protect life, property and the
environment through a comprehensive fire and life safety program that ensures an adequate
and timely response to emergencies. The Public Facilities Plan, as part of the Comprehensive
Plan, indicates:
County-wide Fire & EMS Service Information & Needs
New 5
Recommendations for Fire Stations
by 2022
Replacement/Revitalization 4
Fire 24%
1
2011 Incidents as a percent of total
EMS (Emergency Medical Services) 76%
Fire/EMS Increases in Call Volume
44%
from 2001 and 2011
County Population Increase from
17%
2001 to 2011
1
With the aging of population, medical emergency incidents are expected to increase faster than the rate of
population growth over time.
Fire Service - Project Impacts
Estimated Number of Calls for
15
Service Annually
Reference “Financial Impact on Capital Facilities”
Applicant’s Proposal to Address
section
1
Impacts
Proffered Condition
1
The financial impact of residential development on fire facilities is addressed in the “Financial Impact on Capital
Facilities” section of the report.
Additional Information:
When the property is developed, the number of hydrants, quantity of water needed for fire
protection, and access requirements will be evaluated during the plans review process.
Information relative to nearby fire and emergency service facilities can be found in Attachment
3
816SN0517-2015OCT28-BOS-RPT
PARKS AND RECREATION
Staff Contact: Brian Geouge (318-8720) geougeb@chesterfield.gov
The County supports a high-quality park system to provide residents and visitors with equitable
access to active and passive recreation opportunities. The Public Facilities Plan, as part of the
Comprehensive Plan, indicates:
County-wide Parks and Recreation Needs
Park TypeNumber of New Parks Aggregate Acreage
Regional 3600
Community10 790
Neighborhood 9180
Special Purpose 3 1 -
Urban 2 - -
Linear 3 - -
1
The Public Facilities Plan notes facility recommendations for water-based parks. All other facilities are acquired
and developed on a site-by-site basis.
2
Facilities are recommended in urban areas where there is limited acreage available for park development.
3
Facility needs are assessed on a site-by-site basis as recommended in the Public Facilities Plan.
Parks and Recreation – Project Impacts
5.9 Acres of Regional, Community and/or Neighborhood
2012County Level of Service
parkland per 1,000 persons
9 Acres of Regional, Community and/or Neighborhood
Target Level of Service
parkland per 1,000 persons
Applicant’s Proposal to Address Reference “Financial Impact on Capital Facilities” section
1
Impacts Proffered Condition
1
The financial impact of residential development on parks facilities is addressed in the “Financial Impact on Capital
Facilities” section of the report.
Additional Information:
Information relative to nearby parks and recreation facilities can be found in Attachment 3.
916SN0517-2015OCT28-BOS-RPT
LIBRARIES
Staff Contact: Debra Winecoff (751-4475)winecoffd@chesterfield.gov
The public library system’s role in the county has expanded beyond its traditional function as a
resource for information and materials, and now serves as a community gathering place for
educational, cultural and informational services; community support during emergencies;
economic development; and revitalization activities.The Public Facilities Plan, as part of the
Comprehensive Plan,indicates:
County-wide Library Needs
Facility ActionCounty-wide Facility Needs
Expand or Replace 5 Libraries
Construction of New 5 Libraries
Facilities
1 Community Arts Center
Libraries -Project Impacts
Applicant’s Proposal to Reference “Financial Impact on Capital Facilities” section
1
Address Impacts Proffered Condition
1
The financial impact of residential development on library facilities is addressed in the “Financial Impact on
Capital Facilities” section of the report.
Additional Library Information:
Information relative to nearby library facilities can be found in Attachment 3
1016SN0517-2015OCT28-BOS-RPT
SCHOOLS
Staff Contact: Atonja Allen (804-318-8740) atonja_allen@ccpsnet.net
High performing, high quality public schools contribute to the quality of life and economic
vitality of the County. The Comprehensive Plan suggests a greater focus should be placed on
linking schools with communities by providing greater access, flexible designs and locations that
better meet the needs of the communities in which they are located. The Public Facilities Plan,
as part of the Comprehensive Plan, indicates:
County-wide School Needs
School Types Facilities to Revitalize/Replace New Facilities
Elementary 16 3
Middle 62
High 23
Technical - 1
Schools -Project Impacts
Elementary 10
Middle 5
Average Student Yield
High 7
Total 22
Applicant’s Proposal to Reference “Financial Impact on Capital Facilities” section
1
Address Impacts Proffered Condition
1
The financial impact of residential development on school facilities is addressed in the “Financial Impact on
Capital Facilities” section of the report.
Additional Information:
After review of this request, based on current school assignments and student enrollment the
proposed rezoning case will have an impact on schools. It is possible that over time this case,
combined with other tentative residential developments and other zoning cases in the area will
continue to push these schools to their capacity and therefore impact the capacity of facilities
division-wide.
Information relative to schools currently serving area can be found in Attachment 3.
1116SN0517-2015OCT28-BOS-RPT
COUNTY DEPARTMENT OF TRANSPORTATION
Staff Contact: Jim Banks (804) 748-1037 banksj@chesterfield.gov
Staff Contact: Steve Adams (804-751-4461) adamss@chesterfield.gov
The Comprehensive Plan, which includes the Thoroughfare Plan, identifies county-wide
transportation needs that are expected to mitigate traffic impacts of future growth. The
anticipated traffic impact of the proposal has been evaluated and recommendations are
detailed in the chart below:
Recommendation Applicant’s Proposal
Cash Proffer PolicyReference “Financial Impact on Capital Facilities”
section
Proffered Condition
VIRGINIA DEPARTMENT OF TRANSPORTATION
Staff Contact: Brian Lokker (804-674-2384) brian.lokker@vdot.virginia.gov
VDOT has no comment on this request.
1216SN0517-2015OCT28-BOS-RPT
WATER AND WASTEWATER SYSTEMS
Staff Contact: Jamie Bland (804-751-4439) blandj@chesterfield.gov
This proposal will have a minimal impact on the public utility systems. The proposal’s impacts on
the County’s utility system are detailed in the chart below:
Water and Wastewater Systems
Currently Size of Existing LineConnection Required by County Code?
Serviced?
Water No 8” & 12”Yes
Wastewater No 27”Yes
ENVIRONMENTAL
Drainage, Erosion and Water Quality
Staff Contact: Doug Pritchard (804-748-1028) pritchardd@chesterfield.gov
Environmental Engineering has no comment on this request.
1316SN0517-2015OCT28-BOS-RPT
CASE HISTORY
ApplicantSubmittals
7/6/2015 Application submitted– reduced cash proffer and design standards offered
9/3/2015 Revisions to proffered conditions submitted– cash proffer modified to offer
maximum acceptable cash proffer in accordance with Cash Proffer Policy;
proffered conditions relative to design standards withdrawn(Reference
Supplemental Information offered by Budget Department – Attachment 4)
Community Meeting
8/6/2015 Issues Discussed:
Applicant proposes to add quality to the development to reduce current
cash proffer($22,734) to $14,225 per unit
Drainage issues in Surreywood
Reduction in cash proffer would result in less money available for public
facilities
Area traffic concerns; traffic will increase with development
Reduced sales prices would reduce home values for neighbors
Questioned relationship between landscaping/street trees and cash
proffer reduction
People leaving area because of area schools
Construction planned to begin in 3 to 6 months
Planning Commission Meeting
9/15/2015 Citizen Discussion
No one spoke to support or oppose the case
Commission Discussion
Mr. Gulley expressed concern that greater consideration was not given
incentivize quality development for the reduced cash proffers since the
property is within a revitalization area. He noted that a comprehensive
strategy in revitalization areas was needed and added that Planning, Budget
and revitalization efforts should be coordinated in cases where incentives are
proposed for development in revitalization areas.
Recommendation: APPROVAL AND ACCEPTANCE OF THE
PROFFERED CONDITION IN ATTACHMENT 1
Motion: Gulley Second: Wallin
AYES: Gulley, Waller, Brown, Patton and Wallin
The Board of Supervisors on Wednesday, October 28, 2015, beginning at 6:30 p.m., will
consider this request.
1416SN0517-2015OCT28-BOS-RPT
ATTACHMENT 1
PROFFERED CONDITION
Note:
(STAFF/CPC) – Recommended by the Planning Commission and Staff
With the approval of this request, Proffered Condition 2 of Case 06SN0141 shall be amended as
outlined below. All other conditions of Case 06SN0141 shall remain in force and effect
Cash Proffer. For each dwelling unit, the applicant, sub-divider, or assignee(s)
(STAFF/CPC)
shall pay the following to the County of Chesterfield, prior to the issuance of a
building permit for infrastructure improvements within the cash proffer service
district for the property, unless state law prevents enforcement of that timing:
a)$18,966 per dwelling unit for the period beginning the July 1 preceding
the Board of Supervisors’ approval of the case through July 1 four years
later, at which point the amount will be adjusted for the cumulate change
in the Marshall and Swift Building Cost index during that time period.
b)Thereafter, the per dwelling unit cash proffer amount shall be
automatically adjusted, annually, by the annual change in the Marshall
and Swift Building Cost Index on July 1 of each year.
c)Cash proffer payments shall be spent for the purposes proffered or as
otherwise permitted by law.
d)Should Chesterfield County impose impact fees at any time during the life
of the development that are applicable to the Property, the amount paid
in cash proffers shall be in lieu of or credited toward, but not be in
addition to, any impact fees in a manner determined by the County. (B)
1516SN0517-2015OCT28-BOS-RPT
ATTACHMENT 2
CASE 06SN0141
1616SN0517-2015OCT28-BOS-RPT
1716SN0517-2015OCT28-BOS-RPT
1816SN0517-2015OCT28-BOS-RPT
1916SN0517-2015OCT28-BOS-RPT
2016SN0517-2015OCT28-BOS-RPT
2116SN0517-2015OCT28-BOS-RPT
ATTACHMENT 3
SUPPLEMENTAL PUBLIC FACILITIES STATISTICS
Schools Currently Serving Area
A.M. Davis
Providence Monacan
Elementary
Middle School High School
School
Capacity
nal
Functional Functional
MembershipMembershipMembership
% Capacity% Capacity% Capacity
CapacityCapacityCapacity
Categories
Functio
Current
and
Projected
2014 683 634108862 1057 82 13991757 80
2
Figures
2015 699 -110876 - 83 1418- 81
2016 710 -112896 - 85 1422- 81
2021 749 -118962 - 91 1433- 82
Trailers Number of
4 - -
1
Trailers
1
Trailers are not identified in the staff report for schools under 90% capacity.
2
Disclaimer: Please note that Projected Membership AND Functional Capacity are updated on an ANNUAL BASIS.
They are based on the September 30 membership and Space Utilization Study Report for a given year. School
boundary adjustments may be made to address over capacity levels.
Nearby Public Facilities
Fire Station Wagstaff Fire Station, Company Number 10
EMS Facility Forest View Volunteer Rescue Squad
Library La Prade and new Reams-Gordon Libraries
Parks & Recreation Rockwood Park and Manchester, Providence and Davis Athletic
Complexes
2216SN0517-2015OCT28-BOS-RPT
ATTACHMENT 4
SUPPLEMENTAL INFORMATION
BUDGET AND MANAGEMENT - IMPACTS ON COUNTY’S REVITALIZATION EFFORTS
Staff Contact: Natalie Spillman (717-8767) spillmann@chesterfield.gov
Staff initially conducted a review of this application particularly as it relates to the County’s
revitalization initiative. There are a myriad of activitiesunderway that are focused on
revitalizing key areas of the county. Staff first elected not to include the findings of that review
in the published staff report since the applicant modified their proffers after receiving staff’s
feedback. Staff believes that while the case now contains proffers that are different than what
was presented at the time of that review, that the Commission and Board of Supervisors would
benefit from understanding staff’s approach to reviewing the earlier conditions included with
this application.
Key factors that led staff to take a unique approach to the review of this case are noted as
follows:
BACKGROUND ELEMENTS
This project is located within the boundary of the Providence Middle School
revitalization area (“The Area”).
Existing home values in The Area, on average, are approximately 32 percent below the
countywide average assessed value.
The county is focusing resources in a variety of ways to aid in the revitalization efforts in
The Area:
The County is focusing resources on neighborhood enhancement inspections in
o
several subdivisions in The Area surrounding the subject property (encompassing
more than 800 homes).
County planned capital investments (through FY2020) in The Area include:
o
$25.9 million in school renovations (Providence Middle School)
Installation of sidewalks ($1.4 million)
Improvements to parks to include turf, parking/driveway, paths, lighting
($783,000)
Replacement waterlines ($462,000)
The applicant has indicated that the new home values of the proposed development are
targeted to be 30 percent higher than the average assessed values of surrounding
homes.
The proposed development has relatively few proposed new homes (45 new units).
The proposed project has the potential to spur other new development on at least two
other acreage parcels designated for residential uses and of sufficient size for future
development.
FINDINGS
Earlier in the review process for this case, the applicant submitted a variety of ‘design standard’
proffered conditions, seeking $4,500 per dwelling unit in relief to the cash proffer. The proffers
2316SN0517-2015OCT28-BOS-RPT
submitted by the applicant ranged from landscaping requirements to types of acceptable siding
material. However, after a thorough review by staff, looking at the developed properties
surrounding the subject property, it was determined that the applicant’s proffers were not
providing substantially different improvements to the new property than those found in the
existing surrounding homes. Subsequently, the applicant withdrew the ‘design standards’ and
increased the cash proffer by $4,500 per dwelling unit. Some level of relief to the cash proffer
could have been supported had the proffered conditions for ‘design standards’ more notability
differentiated this development from surrounding existing properties.
2416SN0517-2015OCT28-BOS-RPT