19SN0622
CASE NUMBER: 19SN0622
APPLICANT: Chester Solar Technology Park, LLC
CHESTERFIELD COUNTY, VIRGINIA
BERMUDA DISTRICT
ANALYSIS AND
RECOMMENDATION
Board of Supervisors (BOS) Hearing:
SEPTEMBER 25, 2019
BOSTime Remaining:
365 DAYS
Contact:
SARA BORN (303-775-1773)
BRENNEN KEENE (804-775-1005)
Planning Department Case Manager:
1,665.1 Acres 13301 Bradley Bridge Road
DARLA ORR (804-717-6533)
REQUEST
Rezoning from Agricultural (A), Regional Business (C-4) and Residential (R-12) to Agricultural (A)
with Conditional Use to permit a large scale solar energy facility, electric power transforming
substation and switchyard, data center, above ground water storage tank with communications
antenna, and wastewater pumping station uses plus Conditional Use Planned Development to
permit exceptions to ordinance requirements.
Notes:
A. Conditions may be imposed or the property owner may proffer conditions.
B.Proffered Conditions, Textual Statement, Exhibit and Solar Ordinance are located in Attachments 1-4.
SUMMARY
A 150 MWAC large scale solar energy facility and associated equipment, such as an electric
transforming substation and switchyard, to accommodate interconnection with the electric utility
grid; one (1) data center on 300 acres; two (2) above ground water storage tanks with collocated
communications antenna; and a regional wastewater pumping station are proposed. These uses
require approval of a Conditional Use in an Agricultural (A) District. A recent ordinance
amendment establishes specific standards for solar energy facilities that address: general layout,
location, access, anticipated locations of transmission lines, facility decommissioning,
certifications of state and federal approvals, construction activities limits, setbacks, buffers, health
and safety, and facility operation and design.
The proposed uses will comply with Zoning Ordinance standards, except that approval of
Conditional Use Planned Development is requested to eliminate setback requirements from
adjacent properties owned by Virginia Electric and Power Company containing overhead electric
distribution lines which run internal through the subject property and to permit increased heights
for data center building(s) and the water tanks.
A conceptual plan identifies the general locations of these uses. (Exhibit A)
Dedication of a conservation easement around an existing lake and 30-foot wide trail easement
around the perimeter of the property is planned.
Providing a FIRST CHOICE community through excellence in public service
RECOMMENDATIONS
PLANNING APPROVAL
COMMISSION
PLANNING APPROVAL
Proposal complies with Plan relative to land uses, transition and parcel
aggregation
STAFF
Planned solar facility complies with Zoning Ordinance standards for such
use
As conditioned, impacts on area residential uses minimized
TRANSPORTATION - APPROVAL
219SN0622-2019SEPT25-BOS-RPT
319SN0622-2019SEPT25-BOS-RPT
Comprehensive Plan
Classification:
CORPORATE OFFICE/RESEARCH/LIGHT INDUSTRIAL & REGIONAL MIXED USE
The designation suggests the property is appropriate for corporate office, laboratories, and light and
some moderate manufacturing uses and an area of integrated and highly concentrated office,
commercial and higher density residential use. Aggregation/master planning properties to achieve land
use compatibility, transition, adequate transportation improvements and economic development
.
potential is also suggested
Surrounding Land Uses and Development
Bradley Bridge
Rd.
Single family uses
Branders
Larger acreage parcels
Bridge Rd.
Single family uses
Stoney Glen &
Stoney Glen South
Single family uses - Glebe
Point, Glebe Point Estates
& Matoax Hundred
419SN0622-2019SEPT25-BOS-RPT
PLANNING
Staff Contact: Darla Orr (804-717-6533) orrd@chesterfield.gov
Zoning History
Case Number Request
Rezoning to Residential (R-12) of 1,445.4 acres and to Regional Business (C-4)
of 169.1 acres with Conditional Use to permit a wastewater pump station and
Conditional Use Planned Development to permit exceptions to ordinance
standards
06SN0244
Master-planned residential development with 4,998 units (single family,
Approved
cluster, townhome and multi-family) and 470,000 of neighborhood and
(09/2007)
regional commercial uses proposed
Approval included construction of transportation network to accommodate
planned development and phasing for road construction/dedication; use
limitations; recreational and pedestrian amenities; and specific development
standards for each housing type and commercial area
Proposal
A 150 MWAC large scale solar energy facility and associated equipment, such as an electric
transforming substation and switchyard, to accommodate interconnection with the electric
utility grid; one (1) data center on 300 acres; two (2) above ground water storage tanks with
collocated communications antenna; and a regional wastewater pumping station are proposed.
These uses require approval of a Conditional Use in an Agricultural (A) District. Development of
the property will generally conform to the Conceptual Plan. (Exhibit A Attachment 3)
Large Scale Solar Facility and Electric Interconnection Equipment
Development of the site would comply with recently adopted Zoning Ordinance
standards for large scale solar energy facilities (Zoning Ordinance Attachment 4),
except that the setbacks would not be required from internal property boundaries.
Electric distribution lines are located on these properties owned by Virginia Electric and
Power Company which run through the request property. The 50-foot exception to the
50-foot setback from the internal property lines would be appropriate given necessary
interconnection with these distribution lines.
The Zoning Ordinance requires solar energy facilities to be setback 150 feet from any
residentially zoned or occupied properties and 100 feet from any public road or
thoroughfare road. These setbacks will be met, and greater setbacks are offered for the
substations, switching stations and solar communication and evaluation towers which
would be permitted at a maximum height of 80 feet (Proffered Condition 3). The Zoning
Ordinance regulations for solar energy facilities address: general layout, location,
access, anticipated locations of transmission lines, facility decommissioning,
certifications of state and federal approvals, construction activity limits, setbacks,
buffers, health and safety, and facility operation and design.
The applicants will likely need to selectively remove larger trees within the 100-foot
buffers along the eastern and western boundaries to prevent shading of solar panels.
519SN0622-2019SEPT25-BOS-RPT
The Ordinance permits certain tree removal within a buffer with tree replacement. At
the time of plans review, the applicant will be required to demonstrate, for Planning
Department approval, where tree removal may be needed, and replacement evergreen
planting offered to further mitigate views of the solar facility (Proffered Condition 11).
Selective tree removal would be permitted within the inward 25 of the 100-foot buffer
along the western property boundary and 30 50 feet of the 100-foot buffer along the
eastern property boundary depending upon the location of the 30-foot trail easement
along Branders Bridge Road. (Proffered Condition 11)
Data Center
Data center use is planned on 300 acres of the request property. While the conceptual
plan identifies four (4) potential locations for the data center, only one (1) data center
site is permitted (Proffered Condition 3 and Conceptual Plan). The exact location will be
determined at the time of plans review. Data center use will comply with Zoning
Ordinance standards except that a height exception would permit the data center to
have a maximum building height of 80 feet. A 100-foot buffer is required adjacent to
any data center site. Greater setbacks than are required by Ordinance are offered for
the data center (300 feet) and a 400-foot setback if offered for any back-up power
generators for the data center. (Proffered Condition 3 and Textual Statement)
Water Tanks With Communications Antenna and Wastewater Pump Station
Two (2) above ground water storage tanks with collocated communications antenna
would be permitted at a maximum height of 199 feet. While the conceptual plan
identifies multiple locations for these water tanks, only two (2) tanks would be
permitted (Proffered Condition 3 and Conceptual Plan). The exact locations will be
determined at the time of plans review. Communications antenna would only be
permitted if mounted to the water tanks. Proffered conditions address tank and
antenna design and color, screening mechanical equipment, security fencing, and
prohibit lighting and signs and logos. A regional wastewater pumping station would also
be permitted, generally as located on the Conceptual Plan. (Exhibit A - Attachment 3)
Lake Conservation Easement and Shared Use Trail
The applicant has offered to dedicate a conservation easement around the on-site lake
as generally identified on the Conceptual Plan (Proffered Condition 4 and Conceptual
Plan). A thirty (30) foot wide trail easement is also offered around the perimeter of the
property. This shared use trail will become part of the North-South Trail, as identified
4). In addition, a one (1)
acre area for future parking and access for the North-South Trail in a location agreeable
to the Applicant and the County will be dedicated to the County. The developer of the
data center will be required to construct the portion of the trail along Branders Bridge
Road. (Proffered Condition 8)
As proposed, the anticipated land uses, buffering and setbacks provide an appropriate
transition to neighboring residential uses. As such, staff is supportive of this request.
619SN0622-2019SEPT25-BOS-RPT
COUNTY TRANSPORTATION
Staff Contact: Steve Adams (804-748-1037) adamst@chesterfield.gov
In September 2007, the Board approved Case 06SN0244 on the property to permit a maximum
of 4,998 residential units and a maximum of 470,00 square feet of commercial uses. The
development proposal was anticipated to generate 66,800 average daily trips. The applicant
proffered extensive road improvements to address the traffic impact of the proposal.
With this request, the applicant is requesting to rezone the property (1,675.1 acres) back to
Agricultural (A) with a conditional use to permit a large-scale solar energy facility, electric
power transforming station and switch yard, data center, above ground water storage tank and
wastewater pumping station uses. The applicant has indicated the property will be developed
primarily as a large-scale solar energy facility with the potential for a single data center. Trip
generation rates are not available for solar energy facility; however, it is anticipated to be
minimal. Assuming a 1,000,000 square foot data center and using trip generation rates for such
use, a data center could generate approximately 1,000 average daily trips. Traffic generated by
the proposal would be distributed along Branders Bridge Road and Branders Bridge Road.
Branders Bridge Road and Bradley Bridge Road are both identified on the
ŷƚƩƚǒŭŷŅğƩĻ tƌğƓ as major arterials with a recommended right of way width of 90 feet. Both
roads are two-lane facilities. Sections of the roads are substandard, with approximately 10-foot
lane widths and no usable shoulders. VDOT minimum geometric design standards recommend
these roads have 12-foot lane widths and 10-foot shoulders. In 2018, the traffic count on
Branders Bridge Road was 8,600 vehicles per day and Bradley Bridge Road was 3,100 vehicles
per day.
Section 19.1-231 of the County Code outlines the general requirements to meet the needs of
the traffic generated by a proposed development, including acceptable levels of service. The
applicant has offered the following:
Dedications concurrent with Property development (Proffered Condition 4):
45-foot right-of-way dedication along Branders Bridge Rd & Bradley Bridge Rd frontage
30-foot North-South Trail easement for future shared use path (2.5 miles)
30-foot Trail easement surrounding the Property for future shared use path (6.2 miles)
Dedicate one (1) acre to accommodate future parking area for the North-South Trail
Right-of-Way dedications with Completion of Decommissioning (Proffered Condition 4):
200-foot East/West Freeway
90-foot North/South Arterial
90-foot Happy Hill East-West Arterial
Temporary Construction Access (Proffered Condition 5) - To be provided either:
County Property (abandoned railroad right-of-way), from Route 10 to Branders Bridge Rd;
Branders Bridge Rd & Bradley Bridge Rd, if County Property not feasible.
ΛCĻğƭźĬźƌźƷǤ ƚŅ /ƚǒƓƷǤ tƩƚƦĻƩƷǤ ŅƚƩ ĭƚƓƭƷƩǒĭƷźƚƓ ğĭĭĻƭƭ Ʒƚ ĬĻ ĻǝğƌǒğƷĻķ ğƷ ƷźƒĻ ƚŅ ƭźƷĻ ƦƌğƓ͵Μ
719SN0622-2019SEPT25-BOS-RPT
Permanent Vehicular Access (Proffered Condition 5):
Solar Facility: 1 access to Bradley Bridge Rd & 3 accesses to Branders Bridge Rd
Data Center: 1 access to Bradley Bridge Road or Branders Bridge Road.
Staff supports this request.
FIRE AND EMERGENCY MEDICAL SERVICES
Staff Contact: Anthony Batten (804-717-6167) battena@chesterfield.gov
When the property is developed, the number of hydrants, quantity of water needed for fire
protection, and access requirements will be evaluated during the plans review process.
Nearby Fire and Emergency Medical Service (EMS) Facilities
Fire Station The Chester Fire Station, Company Number 1
EMS Facility The Chester Fire Station, Company Number 1
VIRGINIA DEPARTMENT OF TRANSPORTATION
Staff Contact: Willie Gordon (804-674-2907) willie.gordon@vdot.virginia.gov
Site is located on the following state maintained roadways:
Branders Bridge Road (Route 625) is an Urban Minor Arterial with a 35 MPH
o
posted speed limit and a 8,000 AADT (2018)
Bradley Bridge Road (Route 631) is an Urban Collector with a 45 MPH posted
o
speed limit and a 2,900 AADT (2018)
Conceptual site plan does not specify the exact location for proposed commercial entrances
on these two roads. Commercial entrances will be subject to VDOT Access Management
policy and minimum spacing standards.
The applicant may submit site trip generation data to support a lower entrance classification.
VDOT will require the applicant to provide turn lane warrants for any proposed commercial
entrances.
ENVIRONMENTAL ENGINEERING
Staff Contact: Rebeccah Ward (804-748-1028) wardr@chesterfield.gov
Geography
The subject properties generally drain in three directions. The northwestern and western third
drains to the southwest to two unnamed tributaries to Swift Creek. The two tributaries drain
through sections of the Glebe Point subdivision prior to reaching Swift Creek. The northeastern
third drains to the east through three culverts under Branders Bridge Road to Timsbury Creek. The
819SN0622-2019SEPT25-BOS-RPT
southeastern third drains to the south directly into Swift Creek. All of the subject properties are
located within the Lower Swift Creek Watershed.
Natural Resources
A Preliminary Jurisdictional Waters of the U.S. Delineation Package has been prepared and
submitted to the U.S. Army Corps of Engineers for confirmation. Preliminary information provided
in the package indicates the presence of wetlands and streams on the property. Wetlands cannot
be impacted without prior approval from the U.S. Army Corps of Engineers and/or the Virginia
Department of Environmental Quality.
A Resource Protection Area (RPA) Designation must be submitted to the Department of
Environmental Engineering prior to the submittal of any site plans for the confirmation of the
extent of RPA on the properties.
Erosion and Sediment Control
Steep slopes greater than 20 percent are difficult to stabilize when disturbed. The steep slopes on
the subject properties border the onsite tributaries; therefore, disturbance of these slopes will
result in the increased potential for sediment to impact the streams if erosion occurs. These steep
slopes should remain in their natural, undisturbed state to the maximum extent practicable, unless
otherwise approved by the Department of Environmental Engineering. The applicant has offered
Proffered Condition 10.A to address this impact.
Approximately two-thirds of the subject properties drain to the Lakeview Reservoir (also known as
Swift Creek Lake) in Colonial Heights. As a result of steep terrain, the lake could be impacted from
sediment during construction of the properties. Therefore, all sediment basins which will drain in
the direction of the Lakeview Reservoir (also known as Swift Creek Lake) in Colonial Heights shall
be sized twenty-five percent larger than the minimum sizing requirements of the current edition of
the Virginia Erosion and Sediment Control Handbook. In lieu of the larger sediment basins,
enhanced erosion and sediment control measures, such as super silt fence (or alternative as
approved by the Department of Environmental Engineering) and the application of anionic PAM to
denuded areas during construction and final stabilization, may also be provided as directed by the
Department of Environmental Engineering at the time of site plan review. The applicant has
offered Proffered Condition 10.B to address this impact.
PARKS AND RECREATION
Staff Contact: Janit Llewellyn (804-751-4482) llewellynja@chesterfield.gov
Mission
The County supports a high-quality park system to provide residents and visitors with balanced
access to active and passive recreation opportunities. The 2018 level of service is 7.5 acres of
regional, community and neighborhood parkland per 1,000 persons whereas the target level of
service is 9 acres per 1,000 persons.
919SN0622-2019SEPT25-BOS-RPT
Nearby Parks & Facilities
Existing Parks
Harrowgate Park
Chester Linear Park
Kiwanis Park
Chesterfield Community High School
Carver Middle School
Harrowgate Elementary School
Wells Elementary School
Public Facilities Plan
The tǒĬƌźĭ CğĭźƌźƷźĻƭ tƌğƓ identifies the need for a community park near Branders Bridge and
Bradley Bridge roads north of Woodpecker Road.
The Bikeways and Trails Chapter of the Comprehensive Plan recommends provision of
pedestrian/bicycle facilities along all routes shown on the tƌğƓ and connections from these routes
and existing pedestrian/bicycle facilities to adjacent developments. The tƌğƓ shows a route on or
along Bradley Bridge Road.
Parks & Recreation Master Plan
The Parks and Recreation master Plan recommends protection of water resources and riparian
areas and public access where appropriate.
Recommendation
Proposed development should address the Bikeways and Trails Plan recommendations adjacent to
the property along Bradley Bridge Road and conservation goals of the Parks and Recreation Master
Plan.
Summary of Identified Issues
Construction of the pedestrian/bicycle facilities has been offered by the applicant along Branders
Bridge Road as shown on the Bikeways and Trails Plan. Construction of the remainder of the trail
around the property has not been offered.
Additional Parks Comments
There is an opportunity to connect pedestrians from this development to the Bikeways and Trails
and the surrounding community. Other considerations include:
Convert the construction access road to the Chester Linear Trail.
Reserve land in the northeast portion of the property for a future Community Park
between 20 90 acres.
1019SN0622-2019SEPT25-BOS-RPT
1119SN0622-2019SEPT25-BOS-RPT
1219SN0622-2019SEPT25-BOS-RPT
UTILITIES
Staff Contact: Matt Rembold (804-706-7616) remboldm@chesterfield.gov
Existing Water and Wastewater Systems
Currently Size of Closest Existing Connection Required by County
Utility Type
Serviced Lines Code
Water No Yes
Wastewater No Yes
Additional Utility Comments:
This property is located in the mandatory water and wastewater connection area for non-
residential development. Connection to the public water and wastewater systems will be required
by county code. The applicant has offered proffers to connect to public water and wastewater.
(Proffered Condition 9)
There is an existing 16-inch waterline along Glebe Point Road that terminates approximately 1,400
linear feet from the western boundary of the site. There is also an existing 16-inch waterline along
Bradley Bridge Road following the northern boundary line of the site. Both 16-inch waterlines tie
back to the 30-inch water transmission line that conveys water from the Appomattox River Water
Authority water treatment facility into the Courthouse Pressure Zone along Woodpecker Road and
Lewis Road. Elevated water storage and a looped network of adequately sized waterlines will be
necessary to serve this site.
Wastewater service is not immediately available to the site. There is an existing 18-inch
wastewater line that terminates approximately 400 feet from the eastern boundary line of the
site. However, due to the topography of the site, only a very small portion of the site
(approximately 300 acres) can naturally be served by this wastewater line. There is also limited
available capacity (approximately 1.9 MGD) in the wastewater line. The remaining acreage
naturally drains toward Beach Branch and Swift Creek along the southern boundary of the site.
This portion of the site will need a regional wastewater pump station, adequately sized and
located to serve the proposed development and surrounding area. The discharge location of the
pump station shall be determined during detailed engineering design.
The Utilities Department has completed some preliminary engineering on the impact of this
proposed development on its water system and determined that with the current proposed
improvements of a 2 MG elevated water tank and appropriately sized water distribution system
support a data center at this location with a water demand not to exceed 2 MGD. The applicant
the property based on the anticipated demands of all proposed uses prior to any site plan
approvals on the property, this will include the aforementioned utility improvements.
Water demands greater than 2 MGD will require additional water system improvements. This may
include construction of a second elevated water storage tank and offsite pumping and
transmission improvements. These improvements will depend on the actual water demand that
develops on the site. Therefore, the applicant has proffered to participate in their pro-rata share
of all the costs necessary to improve the public water system in order to supply more than 2 MGD
to the site.
1319SN0622-2019SEPT25-BOS-RPT
The applicant has proffered to construct the improvements shown on the Overall Systems Plan to
meet the utility demands of the property. Likewise, the applicant has proffered to dedicate land
and easements for the regional water and wastewater facilities on this property consistent with
the Overall Systems Plan. (Proffered Condition 9)
The Utilities Department supports this case.
1419SN0622-2019SEPT25-BOS-RPT
CASE HISTORY
Applicant Submittals
6/4/19 Application submitted
6/14, 6/17, Revised proffered conditions, Textual Statement and exhibits submitted.
6/18, 6/27,
7/5, 7/22,
8/1 &
8/9/19
Community Meeting
6/25/19 Discussion:
Solar facility to operate for approximately 35 years; afterwards could
continue use (recommission) or discontinue use (decommission); ordinance
requires decommissioning plan
About 500 acres will be developed; remaining acreage remain undisturbed
Industry studies indicate slight increase in temperature from solar energy
heating effects; studies indicate 1 2 degree increase
No data center operator currently identified; solar facility operates separate
Effects on property values; Applicant built near residential use in Arizona
Solar panels absorb light, so no glare; minimal glare from aluminum tracks
that hold panels; unnoticeable by neighbors
No access from solar facility through stubs into adjacent neighborhoods;
Plan to use abandoned CSX railroad bed for access to Route 10 during
construction; if cannot upgrade that area, plan to idge
Road; applicant required to repair any damage from construction traffic
No separate hearing on data center; final location of data center through
site plan review
Smells unlikely from pumping station as raw sewage not accepted
Visibility from adjacent properties; integrity of buffer during winter; visibility
of data center due to proposed building height
Support current proposal over industrial or residential use; less traffic
Fencing planned around pods of solar panels, not entire site
Construction hours to comply with ordinance; daytime; installing piles will
create most noise (60dba at 100 feet); other construction is assembly
Possible livestock on property; plan to use pollinating grass
No effects on area local wells; no utilities for solar use; data center will be
connected to public water and wastewater
on Lewis Road
Federal tax incentives to be used, not local and state tax incentives
Data center use will pay for cost of on-site utilities infrastructure
Support proposed trail and conservation area for public use
1519SN0622-2019SEPT25-BOS-RPT
Planning Commission
7/8/19 Work Session Staff and Applicant presented details of case. There was no
public comment.
7/16/19 ON THEIR OWN MOTION AND WITH
COMMISSION DEFERRED THIS CASE TO THEIR AUGUST 20, 2019 MEETING.
8/20/19 Citizen Comments:
Less traffic than existing zoning; ensure necessary improvements made to
roads
East/West Road dedication delayed until after decommissioning of solar
facility
Demand for water use and two above ground storage tanks; infrastructure
costs should be developers
Question health/environmental risks of solar facilities; ensure
environmental areas protected; not over develop property
Involvement of citizens in zoning process
Timing of trail construction
Support for project; data centers look for green energy
Low impact uses; extremely lower traffic impact
Setbacks for solar facility from adjacent residential uses
Trail to be
trail
Property includes wetlands, steep slopes and Resource Protection Areas
which will be avoided; majority of property will be undisturbed; denuded
areas to be re-seeded with pollinator grasses
Solar panels will not include cadmium; after storm events, repairs made
immediately due to investment of developer
Commission Discussion:
In response to questions from Commissioners, staff clarified that the perimeter
buffers and greater setbacks would minimize visibility of the data center even
with height increase and that the developer will be responsible for constructing
infrastructure to meet public water and wastewater demands
Recommendation APPROVAL AND ACCEPTANCE OF THE PROFFERED
CONDITIONS IN ATTACHMENT 1.
Motion: Sloan Second: Freye
AYES: Jackson, Freye, Jones, Sloan and Stariha
1619SN0622-2019SEPT25-BOS-RPT
ATTACHMENT 1
PROFFERED CONDITIONS
August 9, 2019
Note: Both the Planning Commission and staff recommend acceptance of the following proffered
conditions, as offered by the applicant.
-2298 of the Code of
Virginia (1950 as amended) and the Zoning Ordinance of Chesterfield County, for themselves
and their successors or assigns, proffer that the development of the Property known as
Chesterfield County Tax Identification Number 780-644-8171, 781-637-6541, 781-639-3251,
781-641-6250, 783-635-0505, and 784-641-
developed according to the following conditions if, and only if, the rezoning request for
are granted. In the event the request is denied or approved with conditions not agreed to by
the Developer, the proffers shall immediately be null and void and of no further force or effect.
If the zoning is granted, these proffers and conditions will supersede all proffers and conditions
now existing on the Property.
Exhibit A
revised June 20, 2019.
1.Master Plan. The textual statement last revised July 5, 2019, shall be considered the
Master Plan. (P)
2.Conceptual Plan. Exhibit A shall be considered the Conceptual Plan for the proposed
development. Development of the Property shall conform generally to the Conceptual
Plan and as further provided herein. (P)
3.Uses. The uses permitted on the Property shall be as set forth below:
enter site shall be
i.
allowed on the Property in one of the areas generally shown on Exhibit A,
provided:
The exact location shall be established at the time of site plan
(a)
review.
The Data Center site shall be a maximum of 300 acres.
(b)
The Data Center building shall be set back a minimum of 300 feet
(c)
from the external Property boundaries.
Large scale solar energy facility, including production and storage, and
ii.
ancillary equipment needed to operate and maintain the Solar Facility
Communication Tower co-located with the water storage tanks.
iii.
Two (2) above-
iv.
mounted communications equipment up to a maximum height of one
hundred and ninety-nine (199) feet provided:
1719SN0622-2019SEPT25-BOS-RPT
All mechanical equipment located on or associated with any
(a)
building or structure for the Water Tank shall be screened from
adjacent properties and public rights-of-way in accordance with
the Emerging Growth District standards. This condition shall not
require screening for the Water Tank structure or
communications equipment.
The Water Tank shall be a new composite style elevated water
(b)
storage tank meeting the Utilities Department requirements.
The Water Tank shall be secured by a minimum eight (8) foot high
(c)
fence designed to preclude trespassing.
There shall be no signs or logos permitted on the Water Tank or
(d)
communications equipment.
The Water Tank shall be white, grey, or another neutral color,
(e)
acceptable to the Planning and Utilities Departments. The
communications equipment (antennas, mounting hardware,
cables, etc.) mounted on the outside of the Water Tank shall be
the same or similar color as the Water Tank.
Except for security lighting over the access doors at the base of
(f)
the Water Tank, the Water Tank and communications equipment
shall not be lighted unless required by the Federal Aviation
Administration or the Federal Communications Commission.
Regional Wastewater Pumping Station operated by Chesterfield County
v.
Utilities Department. The Regional Wastewater Pumping Station
together with the various structures and appurtenances shall be
constructed and secured by a minimum eight (8) foot high fence designed
to preclude trespassing.
Utility Interconnection Equipment. The potential locations of utility
vi.
interconnection equipment are shown on Exhibit A. Subject to the
requirements below, the final location and type of utility interconnection
equipment will be determined once the results of the utility
interconnection studies have been completed. A copy of the
interconnection study shall be provided to the Planning Department at
the time of site plan review.
Substations, defined as a series of electrical equipment that
(a)
allows the voltage of energy to be stepped up or stepped down to
meet the transmission line voltage. Any substation needed for
the Solar Facility shall be located a minimum of 150 feet from the
external Property boundaries.
Should a separate substation and/or back-up power generators be
(b)
required for the Data Center, such equipment shall be located a
minimum of 400 feet from the external Property boundaries.
Switchgear Interconnection System(s). A switchgear
(c)
interconnection system is a set of equipment used to connect a
1819SN0622-2019SEPT25-BOS-RPT
lower voltage of energy collected from the Solar Facility to a
utility level distribution system, defined as less than 69 kV. If
provided on the Property, the switchgear interconnection systems
shall be located a minimum of 150 feet from the external Property
boundaries, except for any overhead lines that interconnect onto
existing utility lines.
Switchyard. The utility-owned switchyard serves as the point of
(d)
interconnection and allows the power to go onto the transmission
grid, while also providing a mechanism to isolate the Solar Facility
from the electric grid, if needed. The switchyard is located
directly adjacent to a transmission level electric line and is often
directly adjacent to the substation. Any switchyard shall be
located a minimum of 150 feet from the external Property
boundaries.
Microwave or radio communication equipment, meteorological
(e)
evaluation towers (MET), WMS (Weather Monitoring Station), and
related or similar equipment needed to communicate with
interconnecting utilities, off-takers, and SCADA systems and to
monitor the Solar Facility provided they shall not exceed eighty
(80) feet in height and shall be located a minimum of 300 feet
from the external Property boundaries.
Any use permitted by-right or with restrictions in the Agricultural zoning
vii.
district. (P)
4.Right-of-Way Dedications and Easements.
A.The following rights-of-way shall be dedicated, free and unrestricted, to and for
the benefit of Chesterfield County, prior to the time of issuance of the building
permit for the portion of the Property associated with the building permit.
Forty-five (45) feet of right-of-way on the west side of Branders Bridge
i.
Road immediately adjacent to the Property, measured from the
centerline of the road.
Forty-five (45) feet of right-of-way on the south side of Bradley Bridge
ii.
Road immediately adjacent to the Property, measured from the
centerline of the road.
Dedication of an area for a future parking lot and access to the North-
iii.
South Trail (defined below), not to exceed one (1) acre, at a mutually
agreed location between the Developer and Chesterfield County.
B.The following easements shall be dedicated to and for the benefit of Chesterfield
County prior to the time of issuance of the building permit for the portion of the
Property associated with the building permit. The trail easement locations shall
be determined at the time of site plan review at a mutually agreed location
between the Developer and Chesterfield County and may meander through the
setback/buffer as necessitated by the Property development.
1919SN0622-2019SEPT25-BOS-RPT
-
i.
a future s
Trails Plan, a component of the Comprehensive Plan (approximately 2.5
miles.
Thirty (30) foot trail easement adjacent to the northern, western, and
ii.
southern Property lines, to accommodate a future shared use path
surrounding the Property (approximately 6.2 miles). This trail easement
will provide an easement that encircles the Property and ties into the
North-South Trail at each terminus.
C.Prior to any site plan approval, a phasing plan for the dedications and easements
referenced in Proffered Conditions 4.A. and 4.B., shall be submitted to and
approved by the Transportation Department and such phasing plan shall include
provisions that the first dedication shall not occur prior to site plan approval for
that portion of the Property associated with the site plan. These dedications and
easements shall be made in accordance with the approved phasing plan.
D.Upon the final completion of the decommissioning of the Solar Facility the
following rights-of way shall be dedicated, free and unrestricted, to and for the
benefit of Chesterfield County.
Ninety (90) feet of right-of-way, based on VDOT Urban Minor Arterial (50
i.
mph) standards with modifications approved by the Transportation
Department, for an ea-West
through the Property to the western Property boundary.
Ninety (90) feet of right-of-way, based on VDOT Urban Minor Arterial (50
ii.
mph) standards with modifications approved by the Transportation
Branders Bridge Road at the northern Property line, through the Property
to the East/West Freeway.
Two hundred (200) feet of right-of-way, based on VDOT Rural Principal
iii.
Arterial (60 mph) standards with modifications approved by the
Transportation Department, for an east/west limited access facility
the western Property line to Branders Bridge Road.
E.In the event the Chesterfield County Thoroughfare Plan is modified to reduce or
remove right-of-way dedications or easements referenced in Proffered
Conditions 4.A., 4.B. and 4.C., then those right-of-way dedications or easements
shall be reduced or removed accordingly, as determined by the Transportation
Department. (P and T)
5.Access.
A.Temporary construction access for the Solar Facility from Route 10 to the
Property shall be limited to Tax Identification Number 785-648-2579 (
County at no cost to the Developer (other than permit/licensing fees). If the
Developer determines in good faith that it cannot use the County Property for
2019SN0622-2019SEPT25-BOS-RPT
the temporary construction access due to costs or development impediments
be developed with, and approved, by the Transportation Department. Such
Access Plan may impose reasonable costs on the Developer proportionate to
B.Direct vehicular access, including personal or company vehicles (SU-30 or
smaller) to the Solar Facility shall be permitted to and from Bradley Bridge Road
a
Exhibit A.
C.Except for access to any Water Tank or the Regional Wastewater Pumping
Station, direct vehicular access to the Data Center Site shall be limited to one (1)
entrance/exit to either Branders Bridge Road or Bradley Bridge Road.
D.There shall be no direct vehicular access to Glebe Point Road or Skybird Road in
the Glebe Point Subdivision or Pointer Run Road in the Glebe Point Estates
Subdivision.
E.The exact design and location of each access shall be approved by the
Transportation Department. (T)
6.Road Improvements.
A.If the Developer uses the County Property for temporary construction access,
then prior to commencement of the Solar Facility construction, the Developer
shall construct an adequate temporary construction access road through the
County Property to accommodate construction traffic for the duration of
construction.
B.If the Developer is unable to use the County Property for temporary construction
access, then the Developer shall provide reasonable compensation for damage
caused due to construction traffic on roads used, in accordance with the Access
Plan as referenced in Proffered Condition 5.A. (T)
7.Conservation Easement. Prior to the issuance of the building permit for the land directly
adjacent to the lake, shown on sheet C4.0 on Exhibit A, the developer shall dedicate a
conservation easement, as shown on sheet C4.0 on Exhibit A, to Chesterfield County or
to another party as requested by the County. (P and EE)
8.Trail. The Developer of the Data Center shall construct the North-South Trail referenced
in Proffered Condition 4.B.i. as determined at the time of site plan approval for the Data
Center. (P and P&R)
9.Water and Wastewater.
A.All applicable uses with permanent buildings that require water and wastewater
systems shall be served by county water and county wastewater.
B.The Developer shall provide an Overall Water/Wastewater Systems Plan
or all
proposed uses including the Data Center. The Overall Systems Plan shall be
submitted to the Utilities Department for review and approval prior to the final
2119SN0622-2019SEPT25-BOS-RPT
approval of any site plan for the Property. The Overall Systems Plan shall
include, but not be limited to the following:
A minimum of two (2) adequately sized connections to the Courthouse
i.
Pressure Zone for redundancy, looped through the Property.
A minimum of one (1) adequately sized interconnection between the
ii.
Courthouse and Chester Pressure Zones, at a location acceptable to the
Utilities Department, with any infrastructure necessary for operation of
the interconnection(s).
A minimum of one (1) two-million-gallon elevated Water Tank to be
iii.
constructed at a location with an elevation acceptable to the Utilities
Department. The Water Tank is to be operated in the Courthouse
Pressure Zone unless otherwise approved by the Utilities Department.
The Water Tank is to be constructed in conjunction with the first Data
Center building on the Property and shall be operational prior to the
issuance of the first certificate of occupancy.
Any off-site water and wastewater improvements needed to provide the
iv.
volume of water delivery and wastewater conveyance required for the
development of the Property.
Detailed engineering analysis of the impact the proposed Property
v.
development will have on the existing water and wastewater systems to
determine proposed water and wastewater infrastructure sizing,
locations of facilities, points of connection/interconnection for the water
system and appropriate discharge point for the force main for the
Regional Wastewater Pumping Station.
A Regional Wastewater Pumping Station adequately sized and
vi.
appropriately located to provide service to the Property, adjacent
properties, and the applicable surrounding sewer shed service area.
The improvements proffered herein are the minimum improvements
vii.
needed to support the Property with a water and/or wastewater demand
not to exceed two-million-gallons per day. Should the Property require a
greater water and/or wastewater demand, the Developer shall
participate in its pro-rata share of all the costs necessary to improve the
County water and/or wastewater system to supply the water and/or
wastewater demand generated by the anticipated uses on the Property.
C.The Developer shall construct all improvements shown on the Overall Systems
Plan necessary to meet the demands of the Property. Phased construction of
the Overall Systems Plan improvements shall be allowed to meet the phased
demands of the Property.
D.Following approval of the Overall Systems Plan (developed to accommodate the
construction of regional water or wastewater facilities) and approval of the site
plan for the Solar Facility or Data Center, the mutually agreed utility easements
and dedication of property located on that portion of the Property included
within the site plan and consistent with the Overall Systems Plan shall be
2219SN0622-2019SEPT25-BOS-RPT
provided to the County, at no cost to the County. Dedications of shall be
provided as described below.
Property for each Water Tank, which shall be a minimum of two (2) acres
i.
up to a maximum of five (5) acres, together with the appropriate access
to a public road.
Property for the Regional Wastewater Pumping Station, which shall be a
ii.
minimum of three (3) acres up to a maximum of seven (7) acres, together
with the appropriate access to a public road.
E.Solar Facility equipment installed in accordance with the Overall Systems Plan
shall not be removed to accommodate the regional water and wastewater
facilities, easements, and accesses unless mutually agreed upon by the Solar
Facility, the entity responsible for the water and wastewater facilities
construction, and Chesterfield County. (U)
10.Environmental Engineering.
A.Steep slopes greater than 20% shall remain in their natural, undisturbed state to
the maximum extent practicable except when removal of tall trees is needed to
prevent shading of the solar panels. In such cases, only the trees shall be
removed and all other vegetation shall remain undisturbed and no clearing or
grubbing shall be permitted.
B.For all portions of the Property that drains in the direction of the Lakeview
Reservoir (also known as Swift Creek Lake) in Colonial Heights, one of the
following erosion and sediment control measure shall be used.
All sediment basins shall be sized twenty-five percent (25%) larger than
i.
the minimum sizing requirements of the current edition of the Virginia
Erosion and Sediment Control Handbook.
OR
Enhanced erosion and sediment control measures, such as super silt
ii.
fence (or alternative as approved by the Department of Environmental
Engineering) and the use of anionic PAM during construction will be
provided in accordance with the design and standards set forth by the
Department of Environmental Engineering at the time of site plan review.
C.For the portions of the properties which drain to the west to the Glebe Point
subdivision and east to Branders Bridge Road, the maximum post-development
drainage discharge rate for the 100-year storm shall be based on the maximum
capacity of the existing facilities downstream, and shall not increase the
recorded and/or established 100-year backwater and/or floodplain. On-site
detention of the post-development discharge rate for the 100-year storm to
below the pre-development discharge rate may be provided to satisfy this
requirement. (EE)
11.Buffers. A 100-foot buffer shall be provided in accordance with Zoning Ordinance
requirements and subject to the restrictions below.
2319SN0622-2019SEPT25-BOS-RPT
A.Selective tree removal shall be permitted at the time of plans review provided
the Developer shall demonstrate to the Planning Department where selective
removal of individual trees is necessary, as permitted in the ordinance, and/or is
necessary for removal to limit shading of solar panels.
When the North-South Tra
i.
Bridge Road, removal of taller vegetation within the buffer to limit
shading of solar panels shall be permitted within the westernmost thirty
(30) feet of the 100-foot buffer closest to the Solar Facility.
OR
When the North-South Trail easement is located within the westernmost
ii.
fifty (50) feet of the 100-
removal of taller vegetation within the buffer to limit shading of solar
panels shall be permitted within the westernmost fifty (50) feet of the
buffer closest to the Solar Facility.
Removal of taller vegetation within the buffer located along the western
iii.
Property line to limit shading of solar panels shall be permitted only
within the easternmost twenty-five (25) feet of the 100-foot buffer
closest to the Solar Facility.
B.Where further mitigation of views of the solar facility is needed, the Developer
shall plant continuous evergreen vegetation in the areas where approval is
granted for selective tree removal, unless the Planning Department deems that
remaining existing vegetation within the buffer clearly mitigates visibility of the
Solar Facility from adjacent properties and public rights-of-way. (P)
2419SN0622-2019SEPT25-BOS-RPT
ATTACHMENT 2
TEXTUAL STATEMENT
July 5, 2019
Conditional Use Planned Development ("CUPD") to permit zoning ordinance exceptions, as
described below, for property known as Chesterfield County Tax Identification Number 780-644-
8171, 781 637-6541, 781-639-3251, 781-641-6250, 783-635-0505, and 784-641-6810 (the
Exhibit A
revised June 20, 2019.
1.Setback Exceptions. Solar energy output is critical for a solar facility. To maximize
efficiency it is important that the solar panels received optimal sunlight throughout the
day with minimal shading. In order to minimizing shading and maximize the area for
solar panel installation, no setback shall be required adjacent to Tax ID numbers 781-
639-5686 and 782-644-2839. These parcels are owned by Virginia Electric & Power
Company and used for overhead electric distribution lines.
2.Height Exceptions.
A.Data Center buildings shall be permitted up to a maximum height of eighty (80)
feet.
B.Water Tanks shall be permitted up to a maximum height of one hundred and
ninety-nine (199) feet.
2519SN0622-2019SEPT25-BOS-RPT
ATTACHMENT 3
EXHIBIT A: MASTER PLAN
June 20, 2019
2619SN0622-2019SEPT25-BOS-RPT
2719SN0622-2019SEPT25-BOS-RPT
2819SN0622-2019SEPT25-BOS-RPT
2919SN0622-2019SEPT25-BOS-RPT
3019SN0622-2019SEPT25-BOS-RPT
3119SN0622-2019SEPT25-BOS-RPT
3219SN0622-2019SEPT25-BOS-RPT
3319SN0622-2019SEPT25-BOS-RPT
3419SN0622-2019SEPT25-BOS-RPT
3519SN0622-2019SEPT25-BOS-RPT
3619SN0622-2019SEPT25-BOS-RPT
ATTACHMENT 4
ZONING ORDINANCE
SECTION 19.1-52 SOLAR FACILITIES
Sec. 19.1-52. Uses Generally.
OOO
D. Special Limitations for Specific Uses
. The following uses shall be subject to the
limitations as specified:
OOO
Solar energy facility, large scale.
4.Unless modified or otherwise conditioned by the
Board of Supervisors at time of zoning approval, large scale solar energy facilities
shall be subject to the following limitations and requirements:
a. Project description. In addition to other application requirements, application for
a facility must include project overview in textual form that includes estimated
completion date and operational lifespan of facility, approximate rated capacity of
solar energy system, specified types of solar equipment to be placed on site and
description of any supplementary structures or uses.
b. General plan. General layout plan shall be provided with application. The plan
shall include, at a minimum, location, access points, anticipated location of
transmission lines and other utility connections, general location of solar
equipment and supplementary facilities to be placed on site, buffers and other
items required for zoning applications layout plans. If facility development is to
be phased, a general phasing plan should also be included.
c. Decommissioning plan. A decommissioning plan shall be submitted for review
with initial site plan. A decommissioning plan shall include the following:
Contact information for the party responsible for site decommissioning;
Timeline for, and written description of, decommissioning procedures which
shall include, but not be limited to, removal of any above and below ground
tanks, cables, fencing, debris, buildings, structures or equipment, to include
foundations and pads, related to the facility and the restoration of solar facility
land and related disturbed areas to a natural condition or other approved state.
At time of zoning approval, the Board of Supervisors may approve and
condition a request by an applicant to have certain items intended to be
utilized to serve a permitted use on the site, to remain provided site plan
approval is obtained;
of 3 feet and restoration of site vegetation and topography to pre-existing
condition, provided that the exact method and final site restoration plan shall
be subject to site plan review giving, among other things, consideration to
impacts upon future site use, environmental and adjacent property impacts.
The director of planning may approve a request by the landowner for
3719SN0622-2019SEPT25-BOS-RPT
alternatives to site restoration to allow roads, pads or other items which will
serve a future permitted site use to remain. Where applicable, if the director of
planning determines that a restoration plan significantly deviates from the
description and conditions approved by the Board such plan shall require
amendment of conditions through the zoning process;
A detailed estimate of the cost of decommissioning, which may include net
salvage value of such equipment, facilities or devices, and site restoration or,
if approved by Board of Supervisors, future site development. If
decommissioning is phased then such costs shall be so described and
calculated to match phased plan. An estimate shall be prepared by an
engineer licensed in the state of Virginia, having expertise in the removal of
solar facilities and site restoration as applicable to request;
Decommissioning plan, accompanying estimates and surety shall be updated
every five years and provided to the director of planning; and
Landowner, applicant or facility owner shall provide the county with a surety,
acceptable to the director of planning, equal to the estimated costs of the
decommissioning and site restoration or redevelopment as applicable. Any
such surety shall be provided prior to site plan approval for the facility and
shall include the ability for automatic adjustment for inflation or as necessary
based upon decommissioning and/or restoration plan update.
d. Airport and Federal Aviation Administration (FAA) approval. Prior to site plan
approval, applicant shall demonstrate compliance with glint and glare standards of
the FAA and approval from and the FAA.
e. Construction and decommissioning activity. Except as provided herein, all
construction and decommissioning activity shall be limited to the hours of 7 AM
to 7 PM Monday through Saturday. Pile driving activity will be further limited to
the hours of 9 AM to 5 PM Monday through Saturday. On Sunday, construction
and decommissioning activity will be limited to the hours of 9 AM and 5 PM, and
further restricted only to light construction or decommissioning activity that does
not include pile driving, use of heavy equipment or any other activity that exceeds
60 dBA as measured at property line with any adjacent property not part of
facility.
f. Traffic management plan. When determined by the directors of planning and
transportation that construction or decommissioning activity for the site creates a
significant traffic or safety impact upon or damage to area roads or properties, a
traffic management plan shall be provided at time of site plan review, which shall
include a reasonable road maintenance plan if appropriate under the
circumstances.
3819SN0622-2019SEPT25-BOS-RPT
g. Setbacks, buffers and screening.
The solar facility operational area, to include any buildings, structures,
equipment, parking and disturbed areas, shall be setback a minimum 150 feet
from any residentially zoned or occupied property, 100 feet from any road or
right-of-way shown on the Thoroughfare Plan, and 50 feet from any other
road or property;
Except where adjacent to electric power facility producing electricity for
others or residentially zoned or occupied property, a buffer shall be provided
equal to the required setback. Adjacent to residentially zoned or occupied
property, the buffer shall be 100 feet in width. Each buffer shall comply with
requirements of Perimeter Landscaping C and the requirements of buffers in
this chapter; and
Excluding solar panel arrays, facility outdoor equipment or storage shall be
screened unless determined through site plan review that provided buffer is
sufficient to mitigate view from adjacent property or road.
h. Access. Access to the property shall be provided for Chesterfield County Fire
Department, and where necessary Environmental Engineering, in a manner
satisfactory to each department as determined at time of plan review.
i. Facility operation and design.
Facility design, construction and installation shall conform to applicable
industry standards, including those of the American National Standards
Institute (ANSI), Underwriters Laboratories (UL), the American Society for
Testing and Materials (ASTM), or other similar certifying organizations, and
shall comply with the Uniform Statewide Building Code and with all other
applicable fire and life safety requirements. The type, and manufacturer
specifications of, solar panels shall be submitted for review and approval as
part of the site plan application and may be modified through request to, and
approval, by the director of planning;
Prior to start of electricity transmission, documentation shall be provided to
the director of planning verifying interconnection agreement or similar
agreement with the applicable public utility pursuant to a Power Purchase
Agreement (PPA) or other off-taker as permitted by state law or the State
Corporation Commission, and notification of when electricity transmission is
to begin. The director of planning shall be notified certified mail within 30
days of cessation of such agreement. Where such power distribution is
permitted by law, agreements for power distribution which do not require a
PPA shall also comply with the above documentation and notification;
3919SN0622-2019SEPT25-BOS-RPT
Generation of power shall be limited to photovoltaic panels, provided that any
on-site buildings may utilize integrated photovoltaic building materials;
Solvents necessary for the cleaning of solar panels shall be biodegradable;
Wiring, excluding that which is on a solar array, shall be located underground
except where necessary to directly connect to public service corporation;
Solar panels shall be placed so as to prevent concentrated solar radiation, heat
or glare being directed onto other properties or roads;
Onsite lighting shall be the minimum necessary for security or onsite
maintenance and shall comply with Sec. 19.1-205;
Solar equipment shall not be utilized to provide advertising or function as
signs;
Except for initial construction or decommissioning activity, maintenance
periods or emergency conditions which require temporary use of onsite
generator, noise generated by the facility shall not exceed 60 dBA as
measured at property line with any adjacent property not part of facility; and
Facility owner shall develop a maintenance inspection agreement with the
county to provide for inspection of facility and panels.
j. Height. Excluding transmission utility poles serving the site, no buildings,
structures, solar panel arrays or other equipment utilized on the site shall exceed
25 feet in height. The director of planning may approve the permitted height to be
exceeded where due to terrain, screening or other mitigation visibility of a
structure is minimized;
k. Transmission lines. Except for lines that are solely subject to State Corporation
Commission jurisdiction, and where necessary for lines to directly connect to
existing transmission lines, new transmission lines are subject to site plan review
and shall not be located above ground. The director of planning may approve use
of above ground transmission lines where determined during plan review that
such action would mitigate impact upon protected environmental features or there
exist other site-specific features where underground placement of lines is not
feasible.
l. Health and safety. Security fencing shall be provided for areas of facility
operation a minimum of 6 feet in height, having barbed wire or similar along top
and providing secured gates. Alternative method of security may be approved at
time of site plan approval where demonstrated that such method meets or exceeds
intended security of fencing.
4019SN0622-2019SEPT25-BOS-RPT
m. Change of facility owner. The director of planning shall be notified by certified
mail of any change in ownership and, if different, party responsible for
decommissioning of facility within 60 days of such change.
n. Decommission, abandonment and maintenance compliance.
Planning shall be notified by certified mail 30 days prior to the intended
decommissioning of a solar facility;
Damaged or unusable panels or arrays shall be removed from site within 60
days of removal from service;
A solar facility, or any portion thereof, shall be considered abandoned where
not utilized for the generation and distribution of electricity for a continuous
period of six months. The director of planning may extend such time period
where evidence is provided by the facility owner or operator demonstrating
that the failure to utilize the facility for power generation is beyond the
reasonable control of owner or operator, the facility is operationally capable of
generation and has not been abandoned; and
Decommissioning procedures shall be completed within 1 year of
decommissioning notice, abandonment of a solar facility, or a shorter time
period where in writing building official or other county official determines
the facility or some aspect thereof to be unsafe. If facility owner fails to meet
decommissioning requirements or comply with a request for removal or
repair, the county may at its option:
remove and salvage facility equipment and structures and perform related
o
restoration using provided surety. If the decommissioning surety and
salvage recompense is insufficient, the county shall have the right to
recover such costs from facility owner to include legal fees, expenses and
fines; or
pursue legal recourse to have the solar facility, or portion thereof as
o
expense. The county may seek to recover
its costs, legal fees and legal expenses incurred to have the facility
decommissioned in compliance with approved plan.
4119SN0622-2019SEPT25-BOS-RPT